If 9 men and 12 boys can do a piece of work in 4 days and 4 men and 16 boys can do the
same work in 6 days, how long will 6 men and 24 boys take to complete the same work?

Text Solution

Verified by Experts

The correct Answer is:
4 days
Promotional Banner

Similar Questions

Explore conceptually related problems

If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

12 men and 16 boys can do a piece of work in 5 days. 13 men and 24 boys can do the same work in 4 days. How long will 7 men and 10 boys take to do the same work?

While 4 men and 6 boys can do a piece of work in 2 days, 1 man, and 3 boys can do the same work in 6 days. In how many days can 1 man and 1 boy complete the same work?

If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same work in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be A)6 days B)4 days C)8 days D)7 days

If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :

12 men or 30 boys can complete a work in 72 days. How many days will 48 men and 24 boys will take to complete the same work?

2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?

2men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days.In how many days can 2 men and 1 boy do the work?