A and B together can do a piece of work ...

A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. They work together for 8 days. C alone will complete the remaining work in:
A और B एक साथ किसी कार्य को 10 दिनों में कर सकते हैं |B और C इसे एक साथ 15 दिनों में तथा C और A इसे एक साथ 20 दिनों में कर सकते हैं | वे 8 दिनों तक साथ कार्य करते हैं | शेष कार्य पूरा करने में C को अकेले कितने दिन लगेंगे

A

12 days

B

`3 1/5` years

C

16 days

D

`5 1/3` years

Text Solution

Verified by Experts

Promotional Banner

Topper's Solved these Questions

  • SSC CGL MAINS ALL MENSURATION QUES 2018

    PINNACLE|Exercise Exercise|36 Videos
  • SSC MATHS MAINS 2018 TRIGNOMETRY

    PINNACLE|Exercise Exercise|29 Videos

Similar Questions

Explore conceptually related problems

A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:

A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in

A and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A, B and C all working together can do it in

A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :

A and B , working together, can complete a work in 16 days, C and A together can complete it in 32 days and C and B together can complete it in 24 days. They worked together for 12 days. In how many days will C can complete the remaining work ? / A और B एक साथ कार्य करते हुए किसी कार्य को 16 दिनों में कर सकते हैं, C और A इस कार्य को 32 दिनों में कर सकते हैं और C और A इस कार्य को 32 दिनों में कर सकते हैं | उन्होंने 12 दिनों तक साथ कार्य किया | शेष कार्य समाप्त करने में C को कितने दिन लगेंगे ?

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

A and B can do a work in 12 days, B and C can do it in 15 days and C and A can do it in 20 days. If A, B and C work together, then they will complete the same work in: A और B एक कार्य को 12 दिनों में कर सकते हैं, B और C इसे 15 दिनों में कर सकते हैं और C और A इसे 20 दिनों में कर सकते हैं। यदि A, B और C एक साथ कार्य करते हैं, तो वे उसी कार्य को कितने समय में पूरा करेंगे?

PINNACLE-SSC CHSL 2018 QUESTION PAPER-Exercise
  1. By selling an article for Rs2,300, Rekha gains 25%. If she sells it fo...

    Text Solution

    |

  2. A wire is in the shape of a rectangle whose sides are in the ratio 7 :...

    Text Solution

    |

  3. A and B together can do a piece of work in 10 days, B and C together c...

    Text Solution

    |

  4. A man gets a discount of 30% and then 20% on his food bill. How much e...

    Text Solution

    |

  5. If sqrt((1-cosθ)/(1+cosθ)) xx sqrt((cosecθ -cot θ)/(cosecθ +cot θ))= ...

    Text Solution

    |

  6. If (1/(1-sin theta) +1/(1+sin theta)) = 4sec theta, 0^circ lt theta lt...

    Text Solution

    |

  7. Given four different numbers, the average of first three numbers is fo...

    Text Solution

    |

  8. The simplified value of (7/5 div 7/10 of 3/4) div 4/9- (7/16 div 10 1/...

    Text Solution

    |

  9. The price of a commodity is increased by 36% and the quantity purchase...

    Text Solution

    |

  10. If x≠ − 1 , 2 and 5, then the simplified value of {(2(x^3 -8))/(x^2-x ...

    Text Solution

    |

  11. The marked price of an article is rs 400. After allowing a discount of...

    Text Solution

    |

  12. The given Bar Graph presents the number of students enrolled for vocat...

    Text Solution

    |

  13. Two trains of equal length travelling in opposite directions at 72 km/...

    Text Solution

    |

  14. If x+y+z = 19, x^2 + y^2 + z^2 =133, then the value of x^3 + y^3 + z^3...

    Text Solution

    |

  15. If 8(x + y)^3 - (x − y)^3 = (x + 3y) (Ax^2 + Bxy + Cy^2), then the val...

    Text Solution

    |

  16. An article is sold for Rs x. If it is sold at 33 1/3% of this price, t...

    Text Solution

    |

  17. What is the simplified value of 5 div 10 of 10 xx 4 + 4 div 4 of 4xx10...

    Text Solution

    |

  18. In a class of 80 students, the ratio of the urban to the rural is 5 : ...

    Text Solution

    |

  19. The compound interest on a certain sum for 3 years at 15% p.a.,interes...

    Text Solution

    |

  20. The given Bar Graph presents Income and Expenditure (in crores of Rupe...

    Text Solution

    |