150 workers were engaged to finish a pie...

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

Text Solution

Verified by Experts

The correct Answer is:
25 days

Suppose the work is completed in n days. Since 4 workers dropped every day except the first day, the total amount of work done in n days is the sum of n terms of an A.P. with first term 150 and common difference -4.
`therefore` Total amount of work done
`=n/2[2xx150+(n-1)xx(-4)]=n(152-2n)`
Had the workers not dropped, the work would have finished in (n-8) days with 150 workers working each day. Therefore, the total amount of work done in n days is 150 (n-8).
`therefore` n(152-2n)=150(n-8)
`rArrn^(2)-n-600=0`
`rArr(n-25)(n+24)=0`
`rArrn=25`
Thus, the work is completed in 25 days
Promotional Banner

Topper's Solved these Questions

  • PROGRESSION AND SERIES

    CENGAGE PUBLICATION|Exercise CONCEPT APPLICATION EXERICISE 5.4|13 Videos
  • PROGRESSION AND SERIES

    CENGAGE PUBLICATION|Exercise CONCEPT APPLICATION EXERICISE 5.5|10 Videos
  • PROGRESSION AND SERIES

    CENGAGE PUBLICATION|Exercise CONCEPT APPLICATION EXERICISE 5.2|10 Videos
  • PROBABILITY II

    CENGAGE PUBLICATION|Exercise MULTIPLE CORRECT ANSWER TYPE|6 Videos
  • PROPERTIES AND SOLUTIONS OF TRIANGLE

    CENGAGE PUBLICATION|Exercise Archives (Numerical Value Type)|3 Videos

Similar Questions

Explore conceptually related problems

About 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these

In 6 days, 5 masons finished only half of the work. But 3 masons took more days to finish the remaining the work. Why so?

The construction of our main road began in summer on 6/6/2010. It took 1 yr 3 month 18 days to finish the work. Let's calculate to find on which date the road construction work was completed.

A boy saves 1 paisa the first day, 2 paise the second day, 4 paise the third day and 8 paise the fourth day and so on. Find his total savings at the end of 10 days.

8 men can do a piece of work in 15 days. Find in how many days will 10 men finish the same work.