A and B together can do a piece of work ...

A and B together can do a piece of work in 8 days. B alone can do it in 12 days. B alone works at it for 4 days. In how many more days after that could A alone complete it.

A

15 days

B

18 days

C

16 days

D

20 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the information given in the question and use the concepts of work and efficiency. ### Step 1: Determine the work done by A and B together A and B together can complete the work in 8 days. Therefore, their combined work rate (efficiency) per day is: \[ \text{Work rate of A + B} = \frac{1}{8} \text{ (work per day)} \] ### Step 2: Determine the work done by B alone B alone can complete the work in 12 days. Therefore, B's work rate is: \[ \text{Work rate of B} = \frac{1}{12} \text{ (work per day)} \] ### Step 3: Calculate the work done by A alone Let A's work rate be \( \frac{1}{x} \) (where \( x \) is the number of days A takes to complete the work alone). We know that: \[ \text{Work rate of A + Work rate of B} = \text{Work rate of A + B} \] Thus, \[ \frac{1}{x} + \frac{1}{12} = \frac{1}{8} \] ### Step 4: Solve for A's work rate To solve for \( \frac{1}{x} \), we rearrange the equation: \[ \frac{1}{x} = \frac{1}{8} - \frac{1}{12} \] Finding a common denominator (which is 24): \[ \frac{1}{8} = \frac{3}{24}, \quad \frac{1}{12} = \frac{2}{24} \] So, \[ \frac{1}{x} = \frac{3}{24} - \frac{2}{24} = \frac{1}{24} \] Thus, A's work rate is: \[ x = 24 \text{ days} \] ### Step 5: Calculate the total work done by B in 4 days Now, we need to find out how much work B does in 4 days: \[ \text{Work done by B in 4 days} = 4 \times \frac{1}{12} = \frac{4}{12} = \frac{1}{3} \] ### Step 6: Calculate the remaining work The total work is considered as 1 unit. Therefore, the remaining work after B has worked for 4 days is: \[ \text{Remaining work} = 1 - \frac{1}{3} = \frac{2}{3} \] ### Step 7: Calculate the time taken by A to complete the remaining work Now, we need to find out how long it will take A to complete the remaining \( \frac{2}{3} \) of the work: \[ \text{Time} = \frac{\text{Work}}{\text{Efficiency}} = \frac{\frac{2}{3}}{\frac{1}{24}} = \frac{2}{3} \times 24 = 16 \text{ days} \] ### Final Answer A alone can complete the remaining work in **16 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 13(b)|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 13|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 13|15 Videos
  • SIMPLE INTEREST

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet |10 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 18|10 Videos

Similar Questions

Explore conceptually related problems

A and B together can do a piece of work in 5 days and A alone can do it in 30 days. B alone can do the work in how many days?

A and B together can do a piece of work in 12 days and A alone can do it in 18 days. In how many days canBalone do it?

A and B together can do a piece of work in 6 days. A alone can do it in 10 days. What time will B require to do it alone ?

S CHAND IIT JEE FOUNDATION-TIME AND WORK -Question Bank - 13(a)
  1. A and B together can complete a piece of work in 16 days while B and C...

    Text Solution

    |

  2. A and B together can do a piece of work in 8 days. B alone can do it i...

    Text Solution

    |

  3. A man and a boy can do a piece of work in 24 days. If the man works al...

    Text Solution

    |

  4. A and B can do a piece of work in 30 days, while B and C can do the...

    Text Solution

    |

  5. A and B can do a job together in 7 days. A is 1 3/4 times as efficient...

    Text Solution

    |

  6. I can do a piece of work in 8 days, which can be done by you in 10 day...

    Text Solution

    |

  7. X is twice as good as a workman as Y. X finished a piece of work in 3 ...

    Text Solution

    |

  8. A can cultivate 2/5 the of a land in 6 days and B can cultivate 1/3 rd...

    Text Solution

    |

  9. The time taken by 4 men to complete a job is double the time taken by ...

    Text Solution

    |

  10. A , B and C can do a piece of work in 11 days, 20 days and 55 days re...

    Text Solution

    |

  11. A can do a piece of work in 20 days and B in 40 days. A begins the wor...

    Text Solution

    |

  12. A can complete a work in 9 days, B in 10 days and C in 15 days. B and ...

    Text Solution

    |

  13. A can do a piece of work in 4 hours, B and C together in 3 hours, a...

    Text Solution

    |

  14. Ram can do a piece of work in 6 days and Shyam can finish the same wor...

    Text Solution

    |

  15. A is twice as fast a workman as B and together they finish a piece of ...

    Text Solution

    |

  16. A does half as much work as B in one-sixth of the time.If together the...

    Text Solution

    |

  17. A work could be completed in 100 days by some workers. However, due to...

    Text Solution

    |

  18. A man and a boy received 800 as wages for 5 days for the work they ...

    Text Solution

    |

  19. a certain number of persons can complete a piece of work in 55 days. I...

    Text Solution

    |

  20. A can complete a work in 18 days, B can do the same work in half the t...

    Text Solution

    |