Home
Class 7
MATHS
A can complete a work in 9 days, B in 10...

A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

A

6 days

B

8 days

C

9 days

D

5 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Calculate the work done by B and C together in one day. - A can complete the work in 9 days, so A's work in one day = \( \frac{1}{9} \) - B can complete the work in 10 days, so B's work in one day = \( \frac{1}{10} \) - C can complete the work in 15 days, so C's work in one day = \( \frac{1}{15} \) Now, we need to find the combined work of B and C in one day: \[ \text{Work of B + Work of C} = \frac{1}{10} + \frac{1}{15} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 10 and 15 is 30. Converting the fractions: \[ \frac{1}{10} = \frac{3}{30}, \quad \frac{1}{15} = \frac{2}{30} \] Now add them: \[ \frac{3}{30} + \frac{2}{30} = \frac{5}{30} = \frac{1}{6} \] Thus, B and C together can complete \( \frac{1}{6} \) of the work in one day. ### Step 2: Calculate the work done by B and C in 2 days. Since B and C work together for 2 days: \[ \text{Work done in 2 days} = 2 \times \frac{1}{6} = \frac{2}{6} = \frac{1}{3} \] So, B and C complete \( \frac{1}{3} \) of the work in 2 days. ### Step 3: Calculate the remaining work. The total work is considered as 1 (whole work). Therefore, the remaining work after B and C have worked for 2 days is: \[ \text{Remaining work} = 1 - \frac{1}{3} = \frac{2}{3} \] ### Step 4: Calculate the time taken by A to complete the remaining work. A can complete the whole work in 9 days, which means A's work rate is \( \frac{1}{9} \) of the work in one day. To find out how many days A will take to complete \( \frac{2}{3} \) of the work, we set up the equation: \[ \text{Time taken by A} = \text{Remaining work} \div \text{A's work rate} = \frac{2}{3} \div \frac{1}{9} \] This can be simplified as: \[ \frac{2}{3} \times 9 = \frac{2 \times 9}{3} = \frac{18}{3} = 6 \] Thus, A will take 6 days to complete the remaining work. ### Final Answer: A will take **6 days** to complete the remaining work. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 13(b)|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 13|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 13|15 Videos
  • SIMPLE INTEREST

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet |10 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 18|10 Videos

Similar Questions

Explore conceptually related problems

A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:

Ram and Mohan can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days Mohan had to leave and Ram alone completed the remaining work The whole work was completed in:

A and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :

A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C Work together, they will complete the work in :

S CHAND IIT JEE FOUNDATION-TIME AND WORK -Question Bank - 13(a)
  1. A , B and C can do a piece of work in 11 days, 20 days and 55 days re...

    Text Solution

    |

  2. A can do a piece of work in 20 days and B in 40 days. A begins the wor...

    Text Solution

    |

  3. A can complete a work in 9 days, B in 10 days and C in 15 days. B and ...

    Text Solution

    |

  4. A can do a piece of work in 4 hours, B and C together in 3 hours, a...

    Text Solution

    |

  5. Ram can do a piece of work in 6 days and Shyam can finish the same wor...

    Text Solution

    |

  6. A is twice as fast a workman as B and together they finish a piece of ...

    Text Solution

    |

  7. A does half as much work as B in one-sixth of the time.If together the...

    Text Solution

    |

  8. A work could be completed in 100 days by some workers. However, due to...

    Text Solution

    |

  9. A man and a boy received 800 as wages for 5 days for the work they ...

    Text Solution

    |

  10. a certain number of persons can complete a piece of work in 55 days. I...

    Text Solution

    |

  11. A can complete a work in 18 days, B can do the same work in half the t...

    Text Solution

    |

  12. A, B and C can complete a work in 10, 12 and 15 days respectively. ...

    Text Solution

    |

  13. A and B together can complete a work in 12 days. A alone can comple...

    Text Solution

    |

  14. A, B and C can do a piece of work in 20, 30 and 60 days respectivel...

    Text Solution

    |

  15. P can complete a work in 12 days working 8 hours a day. Q can compl...

    Text Solution

    |

  16. If 'b' men can do a piece of work in 'c' days, then the number of days...

    Text Solution

    |

  17. If 16 men or 20 women can do a piece of work in 25 days, in what time ...

    Text Solution

    |

  18. If one man or two women or three boys can do a piece of work in 22 day...

    Text Solution

    |

  19. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  20. A man completes 5/8 of a job in 10 days. At this rate, how many more ...

    Text Solution

    |