A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?

A

18 days

B

21 days

C

24 days

D

27 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's define the work rates of A and B and then find out how many days A alone can finish the work. ### Step 1: Define the work rates Let the amount of work done by B in one day be \( x \). Since A is twice as fast as B, the amount of work done by A in one day will be \( 2x \). ### Step 2: Calculate the combined work rate Together, A and B can complete the work in 14 days. Therefore, in one day, they complete: \[ \text{Work done by A and B together in one day} = x + 2x = 3x \] ### Step 3: Relate the combined work rate to total work Since they finish the work in 14 days, the total work can be represented as: \[ \text{Total work} = \text{Work rate} \times \text{Time} = 3x \times 14 = 42x \] ### Step 4: Calculate the time taken by A alone Now, we need to find out how many days A alone would take to finish the total work of \( 42x \). Since A does \( 2x \) work in one day, the number of days A would take to finish the work is: \[ \text{Days taken by A} = \frac{\text{Total work}}{\text{Work done by A in one day}} = \frac{42x}{2x} = 21 \] ### Conclusion Thus, A alone can finish the work in **21 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Question Bank - 13(b)|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 13|15 Videos
  • TIME AND WORK

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 13|15 Videos
  • SIMPLE INTEREST

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet |10 Videos
  • TRIANGLES

    S CHAND IIT JEE FOUNDATION|Exercise Self Assessment Sheet - 18|10 Videos

Similar Questions

Explore conceptually related problems

A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?

A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?

A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?

A is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?

A is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?

A is twice as good a work man as B together they finish a piece of work in 18 days . In how many days will A alone finish the work ?

Karteek is twice as good a foreman as Raju and together they finish a piece of work in20 days. In how many days willRaju alone finish the work?

M is the thrice as good as work-man as N and together they finish a piece of work in 30 days.In how many days will M alone finish the work?

S CHAND IIT JEE FOUNDATION-TIME AND WORK -Question Bank - 13(a)
  1. A can do a piece of work in 20 days and B in 40 days. A begins the wor...

    Text Solution

    |

  2. A can complete a work in 9 days, B in 10 days and C in 15 days. B and ...

    Text Solution

    |

  3. A can do a piece of work in 4 hours, B and C together in 3 hours, a...

    Text Solution

    |

  4. Ram can do a piece of work in 6 days and Shyam can finish the same wor...

    Text Solution

    |

  5. A is twice as fast a workman as B and together they finish a piece of ...

    Text Solution

    |

  6. A does half as much work as B in one-sixth of the time.If together the...

    Text Solution

    |

  7. A work could be completed in 100 days by some workers. However, due to...

    Text Solution

    |

  8. A man and a boy received 800 as wages for 5 days for the work they ...

    Text Solution

    |

  9. a certain number of persons can complete a piece of work in 55 days. I...

    Text Solution

    |

  10. A can complete a work in 18 days, B can do the same work in half the t...

    Text Solution

    |

  11. A, B and C can complete a work in 10, 12 and 15 days respectively. ...

    Text Solution

    |

  12. A and B together can complete a work in 12 days. A alone can comple...

    Text Solution

    |

  13. A, B and C can do a piece of work in 20, 30 and 60 days respectivel...

    Text Solution

    |

  14. P can complete a work in 12 days working 8 hours a day. Q can compl...

    Text Solution

    |

  15. If 'b' men can do a piece of work in 'c' days, then the number of days...

    Text Solution

    |

  16. If 16 men or 20 women can do a piece of work in 25 days, in what time ...

    Text Solution

    |

  17. If one man or two women or three boys can do a piece of work in 22 day...

    Text Solution

    |

  18. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  19. A man completes 5/8 of a job in 10 days. At this rate, how many more ...

    Text Solution

    |

  20. 10 men and 15 women finish a work in 6 days. One man alone finishes th...

    Text Solution

    |