A can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
(A) 5
(B) 5
(D) 8
(C) 6

A

8

B

5

C

4

D

6

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

Similar Questions

Explore conceptually related problems

A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?

A can do a piece of work in 25 days and B can finish it in 20 days.They work together for 5 days and then A goes away.In how many days will B finish the remaining work?

16 men can finish a work in 24 days and 48 boys can finish the same work in 16 days.12 men started the work and after 4 days 12 boys joined them.In how many days can they finish the remaining work? 6 b.12 c.16 d.none of these

Deepak can do a piece of work in 25 days and Ashok can do the same work in 40 days.They work together for 5days and then Deepak goes away.In how many days will Ashok finish the remaining work?

A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in

LEARN X-TIME & WORK-EXERCISE
  1. Parmod is able to do a pice of work in 15 days and Qasim can do the sa...

    Text Solution

    |

  2. Tanush's firm can lay railway track between two stations in 16 days. N...

    Text Solution

    |

  3. Gaurav, Parit and Gaggi can do a work in 20,30 and 60 days respectivel...

    Text Solution

    |

  4. Sabir is thrice as good as Anish in work. Sabir is able to finish a jo...

    Text Solution

    |

  5. Kalpana can do a particular work in 6 days. Preeti can do the same wor...

    Text Solution

    |

  6. A job can be completed by 6 men and 8 women in 10 days. 26 men and 48 ...

    Text Solution

    |

  7. Raja can do a piece of work in 4 hours. Raja and Praja together can do...

    Text Solution

    |

  8. Preeti can do a work in the same time in which Kanchan and Sudha toget...

    Text Solution

    |

  9. Narinder completes 80% of a work in 20 days. Then Anju also joins and ...

    Text Solution

    |

  10. "SANJAY Book Depot" can print one lakhs books in 8 hours. "DEVINDER &...

    Text Solution

    |

  11. A can finish a work in 18 days and B can do the same work in 15 days B...

    Text Solution

    |

  12. If 3 men and 7 women can complete a work in 10 days and 4 men and 6 wo...

    Text Solution

    |

  13. A and B can finish a work 30 days if they work together. They worked t...

    Text Solution

    |

  14. A can complete a work in 12 days with a working of 8 hours per day. B ...

    Text Solution

    |

  15. Sabir is thrice as good as Anish in work. Sabir is able to finish a jo...

    Text Solution

    |

  16. P,Q and R can complete a work in 12,24 and 6 days respectively. The wo...

    Text Solution

    |

  17. 10 महिलाये एक कार्य को 7 दिनों में पूरा कर सकती है और 10 बच्चे 14 दिनो...

    Text Solution

    |

  18. NiNAl can alone complete a work in 20 days. Suresh is 25% more efficie...

    Text Solution

    |

  19. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  20. Pruthi and Shakil can complete a work in 20 days and 12 days respectiv...

    Text Solution

    |