A man can do a piece of work in 30 hours...

A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone he can do the work in

A

60 hours

B

50 hours

C

25 hours

D

10 hours

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can break it down as follows: ### Step 1: Determine the total work done The man can complete the work in 30 hours. Therefore, if we consider the total work as 60 units (this is the least common multiple of 30 and 20), we can use this to find the efficiencies. ### Step 2: Calculate the efficiency of the man The efficiency of the man can be calculated as: \[ \text{Efficiency of Man} = \frac{\text{Total Work}}{\text{Time taken by Man}} = \frac{60}{30} = 2 \text{ units/hour} \] ### Step 3: Calculate the efficiency of the man and son together When the man works with his son, they can complete the work in 20 hours. Therefore, their combined efficiency is: \[ \text{Efficiency of Man + Son} = \frac{\text{Total Work}}{\text{Time taken by Man + Son}} = \frac{60}{20} = 3 \text{ units/hour} \] ### Step 4: Calculate the efficiency of the son To find the efficiency of the son, we subtract the efficiency of the man from the combined efficiency: \[ \text{Efficiency of Son} = \text{Efficiency of Man + Son} - \text{Efficiency of Man} = 3 - 2 = 1 \text{ unit/hour} \] ### Step 5: Calculate the time taken by the son to complete the work alone Now that we know the efficiency of the son, we can find out how long it will take him to complete the entire work alone: \[ \text{Time taken by Son} = \frac{\text{Total Work}}{\text{Efficiency of Son}} = \frac{60}{1} = 60 \text{ hours} \] ### Final Answer The son can complete the work alone in **60 hours**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A man can do a piece of work in 5 days, but with the help of his son he can do the same work in 3 days. In what time can the son do it alone?

A works twice as fast as B.If both of them can together finish a piece of work in 12 hours, then B alone can do it in

A can do a piece of work in 2 hours, B can do thrice the work in 8 hours and C can do the same work as A in 8 hours. If all of them work together, how long it would take them to complete the work :

A can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?

A ,\ B\ a n d\ C working together can do a piece of work in 8 hours. A alone can do it in 20 hours and B alone can do it in 24 hours. In how many hours will C alone do the same work?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A can paint a house in 45 days and B can do it in 15 days. Along with ...

    Text Solution

    |

  2. If A alone can do a job in 40 days then, in how many days can B alone ...

    Text Solution

    |

  3. A man can do a piece of work in 30 hours. If he works with his son the...

    Text Solution

    |

  4. A and B can do a work in 12 days, B and C can do the same work in 15 d...

    Text Solution

    |

  5. A and B can do a work in 30 days, B and C can do it in 36 days and C ...

    Text Solution

    |

  6. Working together A and B can do a job in 40 days, B and C in 36 days a...

    Text Solution

    |

  7. A and B can do a work in 20 days, B and C can do it in 30 days and C a...

    Text Solution

    |

  8. A and B together can do a work in 12 days. A alone can do this in 20 d...

    Text Solution

    |

  9. A can make a building in 20 days. B can make the same building in 30 d...

    Text Solution

    |

  10. A and B together can complete a work in 12 days and B and C can do it ...

    Text Solution

    |

  11. A can finish a work in 10 days if he works 4 hours per day. B can com...

    Text Solution

    |

  12. A completes 4/5 of a work in 20 days. He then calls in B and they toge...

    Text Solution

    |

  13. A can complete 50% of a job in 9 days and B can complete 25% of the jo...

    Text Solution

    |

  14. A can do 50% of the job in 16 days, B can do (1)/(4)th of the job in 2...

    Text Solution

    |

  15. P can do (1/4)th of work in 10 days, Q can do 40% of work in 40 days a...

    Text Solution

    |

  16. A does (2)/(5) of a work in 9 days. Then B joined him and they togethe...

    Text Solution

    |

  17. John does (1)/(2) piece of work in 3 hours, Joe does (1)/(4) of the re...

    Text Solution

    |

  18. A can complete a piece of work in 25 days. After working for 5 days, r...

    Text Solution

    |

  19. A and B together can complete a work in 12 days. A alone works for 8 d...

    Text Solution

    |

  20. A and B can together complete a task in 18 hours. After 6 hours A leav...

    Text Solution

    |