Home
Class 14
MATHS
A and B together can complete a work in ...

A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

A

48

B

60

C

24

D

30

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break down the information given and calculate the required values. ### Step 1: Determine the total work A and B together can complete the work in 12 days, and B and C can do it in 16 days. We can find the total work in terms of work units. - Work done by A and B in one day = \( \frac{1}{12} \) of the work - Work done by B and C in one day = \( \frac{1}{16} \) of the work To find the total work, we can take the least common multiple (LCM) of 12 and 16. **LCM of 12 and 16 = 48 units of work.** ### Step 2: Calculate the efficiencies Now, we can calculate the efficiencies of A, B, and C. - Efficiency of A and B together = \( \frac{48}{12} = 4 \) units/day - Efficiency of B and C together = \( \frac{48}{16} = 3 \) units/day ### Step 3: Work done by A and B A works for 5 days and B works for 7 days. - Work done by A and B in 5 days = \( 5 \times 4 = 20 \) units ### Step 4: Work done by B and C Now, since A has worked for 5 days, we need to find out how many days B and C worked together. B worked for 7 days, so they worked together for 2 days (7 - 5). - Work done by B and C in 2 days = \( 2 \times 3 = 6 \) units ### Step 5: Total work done Now, we can calculate the total work done so far: - Total work done = Work done by A and B + Work done by B and C - Total work done = \( 20 + 6 = 26 \) units ### Step 6: Remaining work Now, we can find the remaining work: - Remaining work = Total work - Work done - Remaining work = \( 48 - 26 = 22 \) units ### Step 7: Work done by C C completes the remaining work in 13 days. Therefore, we can find C's efficiency: - Efficiency of C = \( \frac{22}{13} \) units/day ### Step 8: Calculate B's efficiency From the previous steps, we know that the combined efficiency of B and C is 3 units/day. Let B's efficiency be \( b \) and C's efficiency be \( c \). - \( b + c = 3 \) - We already found \( c = \frac{22}{13} \). Substituting the value of \( c \): - \( b + \frac{22}{13} = 3 \) To solve for \( b \): - \( b = 3 - \frac{22}{13} \) - Convert 3 to a fraction: \( 3 = \frac{39}{13} \) - \( b = \frac{39}{13} - \frac{22}{13} = \frac{17}{13} \) units/day ### Step 9: Calculate the number of days B can finish the work Now, we can find out how many days B can finish the total work: - Total work = 48 units - Efficiency of B = \( \frac{17}{13} \) units/day Number of days B can finish the work = \( \frac{48}{\frac{17}{13}} = 48 \times \frac{13}{17} = \frac{624}{17} \approx 36.71 \) days. ### Conclusion B can finish the work in approximately 36.71 days, which can be rounded to 37 days. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

(A + B) can do a piece of work in 12 days. (B + C) can do same work in 6(2)/(3) days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?

A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A and B together can do a work in 12 days. A alone can do this in 20 d...

    Text Solution

    |

  2. A can make a building in 20 days. B can make the same building in 30 d...

    Text Solution

    |

  3. A and B together can complete a work in 12 days and B and C can do it ...

    Text Solution

    |

  4. A can finish a work in 10 days if he works 4 hours per day. B can com...

    Text Solution

    |

  5. A completes 4/5 of a work in 20 days. He then calls in B and they toge...

    Text Solution

    |

  6. A can complete 50% of a job in 9 days and B can complete 25% of the jo...

    Text Solution

    |

  7. A can do 50% of the job in 16 days, B can do (1)/(4)th of the job in 2...

    Text Solution

    |

  8. P can do (1/4)th of work in 10 days, Q can do 40% of work in 40 days a...

    Text Solution

    |

  9. A does (2)/(5) of a work in 9 days. Then B joined him and they togethe...

    Text Solution

    |

  10. John does (1)/(2) piece of work in 3 hours, Joe does (1)/(4) of the re...

    Text Solution

    |

  11. A can complete a piece of work in 25 days. After working for 5 days, r...

    Text Solution

    |

  12. A and B together can complete a work in 12 days. A alone works for 8 d...

    Text Solution

    |

  13. A and B can together complete a task in 18 hours. After 6 hours A leav...

    Text Solution

    |

  14. A can do as much work in 4 days as B can do in 5, and B can do as much...

    Text Solution

    |

  15. A can do a work in 8 hours & B can do the same work in 12 hours. If th...

    Text Solution

    |

  16. A can do a work in 6 days, B can do it in 8 days and C can complete it...

    Text Solution

    |

  17. A and B can do a work in 20 days, B and C can do it in 30 days and C a...

    Text Solution

    |

  18. A and B do a work individually on alternate days. If A start the work,...

    Text Solution

    |

  19. A can complete a work in 10 days and B can complete it in 15 days. If ...

    Text Solution

    |

  20. A can do a work in 10 days and B can do the same in 20 days. If they ...

    Text Solution

    |