A completes 4/5 of a work in 20 days. He...

A completes 4/5 of a work in 20 days. He then calls in B and they together finish the remain ing work in 3 days. How long B alone would take to do the whole work?

A

60 days

B

37.5 days

C

45 days

D

25 days

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos
MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A and B together can complete a work in 12 days and B and C can do it ...

    Text Solution

    |

  2. A can finish a work in 10 days if he works 4 hours per day. B can com...

    Text Solution

    |

  3. A completes 4/5 of a work in 20 days. He then calls in B and they toge...

    Text Solution

    |

  4. A can complete 50% of a job in 9 days and B can complete 25% of the jo...

    Text Solution

    |

  5. A can do 50% of the job in 16 days, B can do (1)/(4)th of the job in 2...

    Text Solution

    |

  6. P can do (1/4)th of work in 10 days, Q can do 40% of work in 40 days a...

    Text Solution

    |

  7. A does (2)/(5) of a work in 9 days. Then B joined him and they togethe...

    Text Solution

    |

  8. John does (1)/(2) piece of work in 3 hours, Joe does (1)/(4) of the re...

    Text Solution

    |

  9. A can complete a piece of work in 25 days. After working for 5 days, r...

    Text Solution

    |

  10. A and B together can complete a work in 12 days. A alone works for 8 d...

    Text Solution

    |

  11. A and B can together complete a task in 18 hours. After 6 hours A leav...

    Text Solution

    |

  12. A can do as much work in 4 days as B can do in 5, and B can do as much...

    Text Solution

    |

  13. A can do a work in 8 hours & B can do the same work in 12 hours. If th...

    Text Solution

    |

  14. A can do a work in 6 days, B can do it in 8 days and C can complete it...

    Text Solution

    |

  15. A and B can do a work in 20 days, B and C can do it in 30 days and C a...

    Text Solution

    |

  16. A and B do a work individually on alternate days. If A start the work,...

    Text Solution

    |

  17. A can complete a work in 10 days and B can complete it in 15 days. If ...

    Text Solution

    |

  18. A can do a work in 10 days and B can do the same in 20 days. If they ...

    Text Solution

    |

  19. A can do a work in 15 days and B can do the same in 25 days. If they ...

    Text Solution

    |

  20. A can do a work in 45 days and B can do it in 40 days. Both starts th...

    Text Solution

    |