Home
Class 14
MATHS
A and B together can complete a work in ...

A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

A

60 days

B

36 days

C

45 days

D

24 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the combined work rate of A and B A and B together can complete the work in 12 days. Therefore, their combined work rate (work done per day) can be calculated as: \[ \text{Combined work rate} = \frac{1 \text{ work}}{12 \text{ days}} = \frac{1}{12} \text{ work per day} \] ### Step 2: Express the work rates of A and B Let the work rate of A be \( A \) (units of work per day) and the work rate of B be \( B \) (units of work per day). From the combined work rate, we have: \[ A + B = \frac{1}{12} \] ### Step 3: Calculate the work done by A in 8 days If A works alone for 8 days, the amount of work done by A is: \[ \text{Work done by A in 8 days} = 8A \] ### Step 4: Determine the remaining work The remaining work after A has worked for 8 days can be expressed as: \[ \text{Remaining work} = 1 - 8A \] ### Step 5: Calculate the work done by B in 20 days B alone can complete the remaining work in 20 days, so we can express this as: \[ \text{Work done by B in 20 days} = 20B \] Since this work is equal to the remaining work, we have: \[ 20B = 1 - 8A \] ### Step 6: Set up the equations Now we have two equations: 1. \( A + B = \frac{1}{12} \) 2. \( 20B = 1 - 8A \) ### Step 7: Substitute \( A \) from the first equation into the second From the first equation, we can express \( A \) in terms of \( B \): \[ A = \frac{1}{12} - B \] Substituting this into the second equation gives: \[ 20B = 1 - 8\left(\frac{1}{12} - B\right) \] Simplifying this: \[ 20B = 1 - \frac{8}{12} + 8B \] \[ 20B = 1 - \frac{2}{3} + 8B \] \[ 20B = \frac{3}{3} - \frac{2}{3} + 8B \] \[ 20B = \frac{1}{3} + 8B \] ### Step 8: Solve for \( B \) Now, isolate \( B \): \[ 20B - 8B = \frac{1}{3} \] \[ 12B = \frac{1}{3} \] \[ B = \frac{1}{36} \] ### Step 9: Find the work rate of A Now substituting \( B \) back to find \( A \): \[ A + \frac{1}{36} = \frac{1}{12} \] \[ A = \frac{1}{12} - \frac{1}{36} \] Finding a common denominator (36): \[ A = \frac{3}{36} - \frac{1}{36} = \frac{2}{36} = \frac{1}{18} \] ### Step 10: Calculate the total work The total work can be calculated as: \[ \text{Total work} = \text{(A + B) work rate} \times \text{time} = \left(\frac{1}{12}\right) \times 12 = 1 \text{ work unit} \] ### Step 11: Determine how many days B alone can complete the whole work Since B's work rate is \( \frac{1}{36} \) work units per day, the total time for B to complete the whole work is: \[ \text{Time} = \frac{1 \text{ work}}{B} = \frac{1}{\frac{1}{36}} = 36 \text{ days} \] ### Final Answer B alone can complete the whole work in **36 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

U, V and W together can complete a work in 10 days. If U alone can complete the work in 20 days and V alone can complete the work in 30 days, then in how many days W alone can complete the work?

If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?

If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?

A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. John does (1)/(2) piece of work in 3 hours, Joe does (1)/(4) of the re...

    Text Solution

    |

  2. A can complete a piece of work in 25 days. After working for 5 days, r...

    Text Solution

    |

  3. A and B together can complete a work in 12 days. A alone works for 8 d...

    Text Solution

    |

  4. A and B can together complete a task in 18 hours. After 6 hours A leav...

    Text Solution

    |

  5. A can do as much work in 4 days as B can do in 5, and B can do as much...

    Text Solution

    |

  6. A can do a work in 8 hours & B can do the same work in 12 hours. If th...

    Text Solution

    |

  7. A can do a work in 6 days, B can do it in 8 days and C can complete it...

    Text Solution

    |

  8. A and B can do a work in 20 days, B and C can do it in 30 days and C a...

    Text Solution

    |

  9. A and B do a work individually on alternate days. If A start the work,...

    Text Solution

    |

  10. A can complete a work in 10 days and B can complete it in 15 days. If ...

    Text Solution

    |

  11. A can do a work in 10 days and B can do the same in 20 days. If they ...

    Text Solution

    |

  12. A can do a work in 15 days and B can do the same in 25 days. If they ...

    Text Solution

    |

  13. A can do a work in 45 days and B can do it in 40 days. Both starts th...

    Text Solution

    |

  14. 3 men A, B, C can complete the work in 10, 12 and 15 days. If A, B an...

    Text Solution

    |

  15. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  16. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  17. A, B and C can complete a work in 8, 16 and 24 days respectively. The...

    Text Solution

    |

  18. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  19. A, B and C can do job in 9, 12 and 36 days respectively if they worked...

    Text Solution

    |

  20. If A, B and C can do a job working alone in 12, 18 and 36 days respect...

    Text Solution

    |