Home
Class 14
MATHS
A can do a work in 6 days, B can do it i...

A can do a work in 6 days, B can do it in 8 days and C can complete it in 12 days. If A starts the work and they work in alternatively, then in how many days, the work will be completed?

A

`6(3)/(5)`

B

`7(2)/(3)`

C

`5(2)/(5)`

D

`6(2)/(3)`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how many days A, B, and C will take to complete the work when they work alternately. Here's the step-by-step solution: ### Step 1: Determine the work done by A, B, and C in one day. - A can complete the work in 6 days, so A's work rate is \( \frac{1}{6} \) of the work per day. - B can complete the work in 8 days, so B's work rate is \( \frac{1}{8} \) of the work per day. - C can complete the work in 12 days, so C's work rate is \( \frac{1}{12} \) of the work per day. ### Step 2: Calculate the total work done in a 3-day cycle. In a 3-day cycle: - Day 1: A works and completes \( \frac{1}{6} \) of the work. - Day 2: B works and completes \( \frac{1}{8} \) of the work. - Day 3: C works and completes \( \frac{1}{12} \) of the work. Now, we find the total work done in these 3 days: \[ \text{Total work in 3 days} = \frac{1}{6} + \frac{1}{8} + \frac{1}{12} \] ### Step 3: Find a common denominator and sum the fractions. The least common multiple (LCM) of 6, 8, and 12 is 24. We convert each fraction: - \( \frac{1}{6} = \frac{4}{24} \) - \( \frac{1}{8} = \frac{3}{24} \) - \( \frac{1}{12} = \frac{2}{24} \) Now, adding these fractions: \[ \text{Total work in 3 days} = \frac{4}{24} + \frac{3}{24} + \frac{2}{24} = \frac{9}{24} = \frac{3}{8} \] ### Step 4: Calculate how many such cycles are needed to complete the work. To complete the entire work (1 unit of work), we need to find how many cycles of 3 days are required: \[ \text{Number of cycles} = \frac{1}{\frac{3}{8}} = \frac{8}{3} \] This means they will complete the work in \( 2 \) full cycles (which is \( 6 \) days) and will have some work remaining. ### Step 5: Calculate the remaining work after 2 cycles. In 2 cycles (6 days), the work done is: \[ \text{Work done in 6 days} = 2 \times \frac{3}{8} = \frac{6}{8} = \frac{3}{4} \] The remaining work is: \[ \text{Remaining work} = 1 - \frac{3}{4} = \frac{1}{4} \] ### Step 6: Determine who will work next and how long it will take to finish the remaining work. On the 7th day, A will work again. A can complete \( \frac{1}{6} \) of the work in one day. To find out how much time A will take to complete the remaining \( \frac{1}{4} \) of the work: \[ \text{Time taken by A} = \frac{\text{Remaining work}}{\text{A's work rate}} = \frac{\frac{1}{4}}{\frac{1}{6}} = \frac{1}{4} \times 6 = \frac{6}{4} = 1.5 \text{ days} \] ### Step 7: Calculate the total time taken. Total time taken = Time for 2 cycles (6 days) + Time taken by A (1.5 days): \[ \text{Total time} = 6 + 1.5 = 7.5 \text{ days} \] ### Final Answer: The work will be completed in **7.5 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 20 days and 25 days. A start the work and they do this work in alternate days. In how many days will this work be completed ?

A and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?

A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?

A can do a piece of work in 8 days, B can do it in 10 days and C can do it in 20 days. In how many days canA, BandCtogether complete the work?

A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?

If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A can do as much work in 4 days as B can do in 5, and B can do as much...

    Text Solution

    |

  2. A can do a work in 8 hours & B can do the same work in 12 hours. If th...

    Text Solution

    |

  3. A can do a work in 6 days, B can do it in 8 days and C can complete it...

    Text Solution

    |

  4. A and B can do a work in 20 days, B and C can do it in 30 days and C a...

    Text Solution

    |

  5. A and B do a work individually on alternate days. If A start the work,...

    Text Solution

    |

  6. A can complete a work in 10 days and B can complete it in 15 days. If ...

    Text Solution

    |

  7. A can do a work in 10 days and B can do the same in 20 days. If they ...

    Text Solution

    |

  8. A can do a work in 15 days and B can do the same in 25 days. If they ...

    Text Solution

    |

  9. A can do a work in 45 days and B can do it in 40 days. Both starts th...

    Text Solution

    |

  10. 3 men A, B, C can complete the work in 10, 12 and 15 days. If A, B an...

    Text Solution

    |

  11. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  12. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  13. A, B and C can complete a work in 8, 16 and 24 days respectively. The...

    Text Solution

    |

  14. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  15. A, B and C can do job in 9, 12 and 36 days respectively if they worked...

    Text Solution

    |

  16. If A, B and C can do a job working alone in 12, 18 and 36 days respect...

    Text Solution

    |

  17. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  18. Ramesh and Rahman can do a work in 20 and 25 days respectively. After ...

    Text Solution

    |

  19. A can do a piece of work in 10 days and B can do it in 12 days. They w...

    Text Solution

    |

  20. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |