Home
Class 14
MATHS
A can do a work in 10 days and B can do ...

A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?

A

10

B

8

C

12

D

9

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work rates of A and B, then calculate how long they work together, and finally find out how many days it takes to complete the work after A leaves. ### Step 1: Determine the work rates of A and B - A can complete the work in 10 days, so A's work rate is: \[ \text{Rate of A} = \frac{1 \text{ work}}{10 \text{ days}} = \frac{1}{10} \text{ work/day} \] - B can complete the work in 20 days, so B's work rate is: \[ \text{Rate of B} = \frac{1 \text{ work}}{20 \text{ days}} = \frac{1}{20} \text{ work/day} \] ### Step 2: Calculate the combined work rate of A and B - When A and B work together, their combined work rate is: \[ \text{Combined Rate} = \text{Rate of A} + \text{Rate of B} = \frac{1}{10} + \frac{1}{20} \] - To add these fractions, we find a common denominator (which is 20): \[ \text{Combined Rate} = \frac{2}{20} + \frac{1}{20} = \frac{3}{20} \text{ work/day} \] ### Step 3: Determine how long they work together before A leaves - Let \( x \) be the number of days they work together. Since A leaves 5 days before the work is completed, B will work alone for 5 days after A leaves. - Therefore, the total time taken to complete the work can be expressed as: \[ \text{Total time} = x + 5 \] ### Step 4: Calculate the total work done - The total work done by A and B together for \( x \) days is: \[ \text{Work done by A and B} = \text{Combined Rate} \times x = \frac{3}{20} \times x \] - The work done by B alone for 5 days is: \[ \text{Work done by B alone} = \text{Rate of B} \times 5 = \frac{1}{20} \times 5 = \frac{5}{20} = \frac{1}{4} \] ### Step 5: Set up the equation for total work - The total work done by both A and B together and B alone must equal 1 (the whole work): \[ \frac{3}{20}x + \frac{1}{4} = 1 \] ### Step 6: Solve for \( x \) - Convert \(\frac{1}{4}\) to a fraction with a denominator of 20: \[ \frac{1}{4} = \frac{5}{20} \] - Substitute this back into the equation: \[ \frac{3}{20}x + \frac{5}{20} = 1 \] - Multiply through by 20 to eliminate the denominator: \[ 3x + 5 = 20 \] - Solve for \( x \): \[ 3x = 20 - 5 \] \[ 3x = 15 \] \[ x = 5 \] ### Step 7: Calculate the total time to finish the work - Since \( x = 5 \), the total time taken to finish the work is: \[ \text{Total time} = x + 5 = 5 + 5 = 10 \text{ days} \] ### Final Answer The work will be finished in **10 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?

P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed

A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

A can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?

A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A and B do a work individually on alternate days. If A start the work,...

    Text Solution

    |

  2. A can complete a work in 10 days and B can complete it in 15 days. If ...

    Text Solution

    |

  3. A can do a work in 10 days and B can do the same in 20 days. If they ...

    Text Solution

    |

  4. A can do a work in 15 days and B can do the same in 25 days. If they ...

    Text Solution

    |

  5. A can do a work in 45 days and B can do it in 40 days. Both starts th...

    Text Solution

    |

  6. 3 men A, B, C can complete the work in 10, 12 and 15 days. If A, B an...

    Text Solution

    |

  7. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  8. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  9. A, B and C can complete a work in 8, 16 and 24 days respectively. The...

    Text Solution

    |

  10. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  11. A, B and C can do job in 9, 12 and 36 days respectively if they worked...

    Text Solution

    |

  12. If A, B and C can do a job working alone in 12, 18 and 36 days respect...

    Text Solution

    |

  13. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  14. Ramesh and Rahman can do a work in 20 and 25 days respectively. After ...

    Text Solution

    |

  15. A can do a piece of work in 10 days and B can do it in 12 days. They w...

    Text Solution

    |

  16. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  17. A and B can do a piece of work in 30 and 36 days respectively. They b...

    Text Solution

    |

  18. A, B and C can do a work separately in 16, 32 and 48 days respectivel...

    Text Solution

    |

  19. Anushka and Anirudh working together can complete a piece of work in 2...

    Text Solution

    |

  20. The working capacity of A is 50% more than that of B. If A can comple...

    Text Solution

    |