Home
Class 14
MATHS
A can do a work in 45 days and B can do ...

A can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?

A

9 days

B

8 days

C

10 days

D

12 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the given information about A and B's work rates and the total time taken to complete the work. ### Step 1: Determine the work rates of A and B - A can complete the work in 45 days, so A's work rate (efficiency) is: \[ \text{Efficiency of A} = \frac{1 \text{ work}}{45 \text{ days}} = \frac{1}{45} \text{ work/day} \] - B can complete the work in 40 days, so B's work rate (efficiency) is: \[ \text{Efficiency of B} = \frac{1 \text{ work}}{40 \text{ days}} = \frac{1}{40} \text{ work/day} \] ### Step 2: Find the LCM of the days to determine the total work - The LCM of 45 and 40 is 360. We can consider the total work as 360 units. ### Step 3: Calculate the efficiencies in terms of work units - A's efficiency in units of work is: \[ \text{Efficiency of A} = \frac{360 \text{ units}}{45 \text{ days}} = 8 \text{ units/day} \] - B's efficiency in units of work is: \[ \text{Efficiency of B} = \frac{360 \text{ units}}{40 \text{ days}} = 9 \text{ units/day} \] ### Step 4: Calculate the total work done by B in 32 days - Since both A and B start the work together and the total work is completed in 32 days, we can calculate the work done by B: \[ \text{Work done by B} = \text{Efficiency of B} \times \text{Time} = 9 \text{ units/day} \times 32 \text{ days} = 288 \text{ units} \] ### Step 5: Determine the remaining work - The total work is 360 units, so the remaining work that A must complete is: \[ \text{Remaining work} = 360 \text{ units} - 288 \text{ units} = 72 \text{ units} \] ### Step 6: Calculate the time taken by A to complete the remaining work - A's efficiency is 8 units/day, so the time taken by A to complete the remaining 72 units of work is: \[ \text{Time taken by A} = \frac{\text{Remaining work}}{\text{Efficiency of A}} = \frac{72 \text{ units}}{8 \text{ units/day}} = 9 \text{ days} \] ### Step 7: Conclusion - Since A worked for 9 days before leaving the work, we conclude that A worked for **9 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?

Krishna can do a work in 10 days while Mohan can do the same work in 20 days. They started work together. After 3 days Krishna left the work and Mohan completed it. For how many days Mohan worked alone more than the number of days required when both worked together ?

A can do a work in 15 days and B in 30 days. If they work on it together, then in how many days will they be able to do 50% of the work?

A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?

A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?

A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A can do a work in 10 days and B can do the same in 20 days. If they ...

    Text Solution

    |

  2. A can do a work in 15 days and B can do the same in 25 days. If they ...

    Text Solution

    |

  3. A can do a work in 45 days and B can do it in 40 days. Both starts th...

    Text Solution

    |

  4. 3 men A, B, C can complete the work in 10, 12 and 15 days. If A, B an...

    Text Solution

    |

  5. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  6. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  7. A, B and C can complete a work in 8, 16 and 24 days respectively. The...

    Text Solution

    |

  8. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  9. A, B and C can do job in 9, 12 and 36 days respectively if they worked...

    Text Solution

    |

  10. If A, B and C can do a job working alone in 12, 18 and 36 days respect...

    Text Solution

    |

  11. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  12. Ramesh and Rahman can do a work in 20 and 25 days respectively. After ...

    Text Solution

    |

  13. A can do a piece of work in 10 days and B can do it in 12 days. They w...

    Text Solution

    |

  14. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  15. A and B can do a piece of work in 30 and 36 days respectively. They b...

    Text Solution

    |

  16. A, B and C can do a work separately in 16, 32 and 48 days respectivel...

    Text Solution

    |

  17. Anushka and Anirudh working together can complete a piece of work in 2...

    Text Solution

    |

  18. The working capacity of A is 50% more than that of B. If A can comple...

    Text Solution

    |

  19. The ratio of the working capacity of A and B is 3: 5. They can do it i...

    Text Solution

    |

  20. Babu and Asha can do together a work in 7 days. Asha is 1(3)/(4) time...

    Text Solution

    |