Home
Class 14
MATHS
3 men A, B and C can complete the work i...

3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C starts work together, A and B left the work 2 days before the comple tion of the work, then the whole work will be finished in how many days?

A

`3(7)/(15)`

B

`5(7)/(15)`

C

5

D

7

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how many days it takes for A, B, and C to complete the work together, given that A and B leave 2 days before the work is finished. ### Step-by-Step Solution: 1. **Determine the Work Rates of A, B, and C:** - A can complete the work in 10 days, so A's work rate is \( \frac{1}{10} \) of the work per day. - B can complete the work in 12 days, so B's work rate is \( \frac{1}{12} \) of the work per day. - C can complete the work in 15 days, so C's work rate is \( \frac{1}{15} \) of the work per day. 2. **Calculate the Combined Work Rate of A, B, and C:** \[ \text{Combined Rate} = \frac{1}{10} + \frac{1}{12} + \frac{1}{15} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 10, 12, and 15 is 60. - Convert each rate: - \( \frac{1}{10} = \frac{6}{60} \) - \( \frac{1}{12} = \frac{5}{60} \) - \( \frac{1}{15} = \frac{4}{60} \) - Now, add them: \[ \text{Combined Rate} = \frac{6 + 5 + 4}{60} = \frac{15}{60} = \frac{1}{4} \] This means A, B, and C together can complete \( \frac{1}{4} \) of the work in one day. 3. **Let the Total Work be 1 Unit:** - If the total work is 1 unit, then the time taken to complete the work by A, B, and C together is: \[ \text{Time} = \frac{1 \text{ unit}}{\frac{1}{4} \text{ unit/day}} = 4 \text{ days} \] 4. **Determine the Work Done Before A and B Leave:** - A and B leave 2 days before the work is completed. Therefore, they work together for \( x - 2 \) days, where \( x \) is the total number of days to complete the work. - In the first \( x - 2 \) days, A, B, and C work together: \[ \text{Work done in } (x - 2) \text{ days} = (x - 2) \times \frac{1}{4} \] 5. **Calculate the Remaining Work Done by C:** - In the last 2 days, only C works: \[ \text{Work done by C in 2 days} = 2 \times \frac{1}{15} = \frac{2}{15} \] 6. **Set Up the Equation for Total Work:** - The total work done is equal to 1 unit: \[ (x - 2) \times \frac{1}{4} + \frac{2}{15} = 1 \] 7. **Solve for x:** - Multiply the entire equation by 60 (the common denominator) to eliminate fractions: \[ 15(x - 2) + 8 = 60 \] \[ 15x - 30 + 8 = 60 \] \[ 15x - 22 = 60 \] \[ 15x = 82 \] \[ x = \frac{82}{15} = 5 \frac{7}{15} \] ### Final Answer: The whole work will be finished in \( 5 \frac{7}{15} \) days.
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A,B and C can complete a work in 10,12 and 15 days respectively.They started the work together.But A left the work 5 days before its completion.B also left the work 2 days after A left.In how many days was the work completed? 4 b.15 c.7 d.8

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A can do a work in 45 days and B can do it in 40 days. Both starts th...

    Text Solution

    |

  2. 3 men A, B, C can complete the work in 10, 12 and 15 days. If A, B an...

    Text Solution

    |

  3. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  4. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  5. A, B and C can complete a work in 8, 16 and 24 days respectively. The...

    Text Solution

    |

  6. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  7. A, B and C can do job in 9, 12 and 36 days respectively if they worked...

    Text Solution

    |

  8. If A, B and C can do a job working alone in 12, 18 and 36 days respect...

    Text Solution

    |

  9. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  10. Ramesh and Rahman can do a work in 20 and 25 days respectively. After ...

    Text Solution

    |

  11. A can do a piece of work in 10 days and B can do it in 12 days. They w...

    Text Solution

    |

  12. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  13. A and B can do a piece of work in 30 and 36 days respectively. They b...

    Text Solution

    |

  14. A, B and C can do a work separately in 16, 32 and 48 days respectivel...

    Text Solution

    |

  15. Anushka and Anirudh working together can complete a piece of work in 2...

    Text Solution

    |

  16. The working capacity of A is 50% more than that of B. If A can comple...

    Text Solution

    |

  17. The ratio of the working capacity of A and B is 3: 5. They can do it i...

    Text Solution

    |

  18. Babu and Asha can do together a work in 7 days. Asha is 1(3)/(4) time...

    Text Solution

    |

  19. The ratio of the working capacity of A and B is 2:3. A takes 10 days ...

    Text Solution

    |

  20. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |