Home
Class 14
MATHS
A, B and C can complete a work in 8, 16 ...

A, B and C can complete a work in 8, 16 and 24 days respectively. They start the work together and A works till last moment . If C leaves the work 2 days before and B leaves one day before the completion of the work, in how many days the work will be finished?

A

8 days

B

5 days

C

6 days

D

7 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Determine the work rates of A, B, and C. - A can complete the work in 8 days, so A's work rate = 1/8 of the work per day. - B can complete the work in 16 days, so B's work rate = 1/16 of the work per day. - C can complete the work in 24 days, so C's work rate = 1/24 of the work per day. ### Step 2: Calculate the combined work rate of A, B, and C. - Combined work rate = A's rate + B's rate + C's rate - Combined work rate = (1/8 + 1/16 + 1/24) To add these fractions, we need a common denominator. The least common multiple (LCM) of 8, 16, and 24 is 48. - (1/8 = 6/48) - (1/16 = 3/48) - (1/24 = 2/48) Now, adding them together: - Combined work rate = (6/48 + 3/48 + 2/48) = 11/48 of the work per day. ### Step 3: Determine the work done before C and B leave. - Let the total work be 48 units (as we took LCM as work). - C leaves 2 days before completion, and B leaves 1 day before completion. ### Step 4: Calculate the work done in the last days. - In the last day, only A works, which means A does 1/8 of the work. - On the second last day, A and B work together, so they do (1/8 + 1/16) of the work. - Work done by A and B together = (1/8 + 1/16) = (2/16 + 1/16) = 3/16 of the work. ### Step 5: Calculate the total work done by A, B, and C before they leave. - Let the total time taken to complete the work be T days. - In the first (T-3) days, A, B, and C work together. They work for (T-3) days at a combined rate of 11/48. - Work done in (T-3) days = (T-3) * (11/48). ### Step 6: Set up the equation for total work. - Total work = Work done by A, B, and C + Work done by A on the last day + Work done by A and B on the second last day. - 48 = (T-3) * (11/48) + (1/8) + (3/16). ### Step 7: Solve for T. - Convert the fractions to a common denominator: - (1/8 = 6/48) - (3/16 = 9/48) - So, the equation becomes: - 48 = (T-3) * (11/48) + (6/48 + 9/48) - 48 = (T-3) * (11/48) + (15/48) - Multiply through by 48 to eliminate the fraction: - 48 * 48 = (T-3) * 11 + 15 - 2304 = 11T - 33 + 15 - 2304 = 11T - 18 - 11T = 2304 + 18 - 11T = 2322 - T = 2322 / 11 - T = 211.09 (approximately 211 days). ### Step 8: Calculate the total days. - Since T is the total time taken, we need to account for the days worked by A, B, and C together, plus the last two days when only A worked. - Total days = T + 2 days (for C leaving) + 1 day (for B leaving) = 211 + 2 + 1 = 214 days. ### Final Answer: The work will be finished in **5 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?

A, B and C can do a work in 8, 16 and 24 days respectively. They all begin together. A continues to work till it is finished, C leaving off 2 days and B one day before its completion. In what time is the work finished?

A, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continously till it is finished , C leaves the work 2 days before its completion and B leaves the work 1 day before its completion . In what time is the work finished ?

A,B and C can complete a work in 10,12 and 15 days respectively.They started the work together.But A left the work 5 days before its completion.B also left the work 2 days after A left.In how many days was the work completed? 4 b.15 c.7 d.8

P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  2. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  3. A, B and C can complete a work in 8, 16 and 24 days respectively. The...

    Text Solution

    |

  4. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  5. A, B and C can do job in 9, 12 and 36 days respectively if they worked...

    Text Solution

    |

  6. If A, B and C can do a job working alone in 12, 18 and 36 days respect...

    Text Solution

    |

  7. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  8. Ramesh and Rahman can do a work in 20 and 25 days respectively. After ...

    Text Solution

    |

  9. A can do a piece of work in 10 days and B can do it in 12 days. They w...

    Text Solution

    |

  10. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  11. A and B can do a piece of work in 30 and 36 days respectively. They b...

    Text Solution

    |

  12. A, B and C can do a work separately in 16, 32 and 48 days respectivel...

    Text Solution

    |

  13. Anushka and Anirudh working together can complete a piece of work in 2...

    Text Solution

    |

  14. The working capacity of A is 50% more than that of B. If A can comple...

    Text Solution

    |

  15. The ratio of the working capacity of A and B is 3: 5. They can do it i...

    Text Solution

    |

  16. Babu and Asha can do together a work in 7 days. Asha is 1(3)/(4) time...

    Text Solution

    |

  17. The ratio of the working capacity of A and B is 2:3. A takes 10 days ...

    Text Solution

    |

  18. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |

  19. A is thrice as good a workman as B. C alone takes 48 days to paint a h...

    Text Solution

    |

  20. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |