Home
Class 14
MATHS
A, B and C can do a job working alone in...

A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?

A

20

B

30

C

18

D

24

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we'll first determine the work done by A, B, and C, and then calculate how long A and B will take to finish the remaining work after C quits. ### Step 1: Determine the work rates of A, B, and C. - A can complete the job in 50 days, so A's work rate is: \[ \text{Work rate of A} = \frac{1}{50} \text{ of the job per day} \] - B can complete the job in 75 days, so B's work rate is: \[ \text{Work rate of B} = \frac{1}{75} \text{ of the job per day} \] - C can complete the job in 20 days, so C's work rate is: \[ \text{Work rate of C} = \frac{1}{20} \text{ of the job per day} \] ### Step 2: Calculate the combined work rate of A, B, and C. To find the combined work rate, we add their individual work rates: \[ \text{Combined work rate} = \frac{1}{50} + \frac{1}{75} + \frac{1}{20} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 50, 75, and 20 is 300. Now we convert each fraction: \[ \frac{1}{50} = \frac{6}{300}, \quad \frac{1}{75} = \frac{4}{300}, \quad \frac{1}{20} = \frac{15}{300} \] Adding these together: \[ \text{Combined work rate} = \frac{6 + 4 + 15}{300} = \frac{25}{300} = \frac{1}{12} \text{ of the job per day} \] ### Step 3: Calculate the total work done in 4 days. Now, we calculate how much work A, B, and C can complete together in 4 days: \[ \text{Work done in 4 days} = 4 \times \frac{1}{12} = \frac{4}{12} = \frac{1}{3} \text{ of the job} \] ### Step 4: Determine the remaining work. Since they completed \(\frac{1}{3}\) of the job, the remaining work is: \[ \text{Remaining work} = 1 - \frac{1}{3} = \frac{2}{3} \text{ of the job} \] ### Step 5: Calculate the work rate of A and B together. Next, we find the combined work rate of A and B: \[ \text{Work rate of A and B} = \frac{1}{50} + \frac{1}{75} \] Using the same common denominator of 300: \[ \frac{1}{50} = \frac{6}{300}, \quad \frac{1}{75} = \frac{4}{300} \] \[ \text{Combined work rate of A and B} = \frac{6 + 4}{300} = \frac{10}{300} = \frac{1}{30} \text{ of the job per day} \] ### Step 6: Calculate the time taken by A and B to finish the remaining work. To find the time \(T\) taken by A and B to complete the remaining \(\frac{2}{3}\) of the job: \[ T = \frac{\text{Remaining work}}{\text{Work rate of A and B}} = \frac{\frac{2}{3}}{\frac{1}{30}} = \frac{2}{3} \times 30 = 20 \text{ days} \] ### Final Answer: A and B will take **20 days** to finish the rest of the job.
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A,B andC can do a job working alone in 12, 16 and 24 days, respectively.In how many days, they can do the job, if they worked together?

A and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?

A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. 3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C ...

    Text Solution

    |

  2. A, B and C can complete a work in 8, 16 and 24 days respectively. The...

    Text Solution

    |

  3. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  4. A, B and C can do job in 9, 12 and 36 days respectively if they worked...

    Text Solution

    |

  5. If A, B and C can do a job working alone in 12, 18 and 36 days respect...

    Text Solution

    |

  6. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  7. Ramesh and Rahman can do a work in 20 and 25 days respectively. After ...

    Text Solution

    |

  8. A can do a piece of work in 10 days and B can do it in 12 days. They w...

    Text Solution

    |

  9. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  10. A and B can do a piece of work in 30 and 36 days respectively. They b...

    Text Solution

    |

  11. A, B and C can do a work separately in 16, 32 and 48 days respectivel...

    Text Solution

    |

  12. Anushka and Anirudh working together can complete a piece of work in 2...

    Text Solution

    |

  13. The working capacity of A is 50% more than that of B. If A can comple...

    Text Solution

    |

  14. The ratio of the working capacity of A and B is 3: 5. They can do it i...

    Text Solution

    |

  15. Babu and Asha can do together a work in 7 days. Asha is 1(3)/(4) time...

    Text Solution

    |

  16. The ratio of the working capacity of A and B is 2:3. A takes 10 days ...

    Text Solution

    |

  17. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |

  18. A is thrice as good a workman as B. C alone takes 48 days to paint a h...

    Text Solution

    |

  19. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |

  20. A,B and C together can finish a task in 7.5 days. C is thrice as produ...

    Text Solution

    |