Home
Class 14
MATHS
A, B and C can do job in 9, 12 and 36 da...

A, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?

A

3

B

4

C

5

D

6

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the process of calculating the work done by A, B, and C, and then determine how long it will take for B and C to finish the remaining work after A leaves. ### Step 1: Determine the work rates of A, B, and C - A can complete the job in 9 days, so A's work rate is \( \frac{1}{9} \) of the job per day. - B can complete the job in 12 days, so B's work rate is \( \frac{1}{12} \) of the job per day. - C can complete the job in 36 days, so C's work rate is \( \frac{1}{36} \) of the job per day. ### Step 2: Calculate the combined work rate of A, B, and C To find the combined work rate when A, B, and C work together, we add their individual work rates: \[ \text{Combined work rate} = \frac{1}{9} + \frac{1}{12} + \frac{1}{36} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 9, 12, and 36 is 36. We can rewrite each fraction: - \( \frac{1}{9} = \frac{4}{36} \) - \( \frac{1}{12} = \frac{3}{36} \) - \( \frac{1}{36} = \frac{1}{36} \) Now, we can add them: \[ \text{Combined work rate} = \frac{4}{36} + \frac{3}{36} + \frac{1}{36} = \frac{8}{36} = \frac{2}{9} \] ### Step 3: Calculate the work done in 3 days Now that we have the combined work rate, we can find out how much work A, B, and C complete together in 3 days: \[ \text{Work done in 3 days} = \text{Combined work rate} \times \text{Time} = \frac{2}{9} \times 3 = \frac{6}{9} = \frac{2}{3} \] ### Step 4: Determine the remaining work The total work is considered as 1 (the whole job). After 3 days, the remaining work is: \[ \text{Remaining work} = 1 - \frac{2}{3} = \frac{1}{3} \] ### Step 5: Calculate the combined work rate of B and C Next, we need to find out how fast B and C can complete the remaining work. Their combined work rate is: \[ \text{Combined work rate of B and C} = \frac{1}{12} + \frac{1}{36} \] Again, we find a common denominator. The LCM of 12 and 36 is 36: - \( \frac{1}{12} = \frac{3}{36} \) - \( \frac{1}{36} = \frac{1}{36} \) Now, we can add them: \[ \text{Combined work rate of B and C} = \frac{3}{36} + \frac{1}{36} = \frac{4}{36} = \frac{1}{9} \] ### Step 6: Calculate the time taken by B and C to finish the remaining work Now we can find the time it takes for B and C to complete the remaining \( \frac{1}{3} \) of the work: \[ \text{Time} = \frac{\text{Remaining work}}{\text{Combined work rate of B and C}} = \frac{\frac{1}{3}}{\frac{1}{9}} = \frac{1}{3} \times \frac{9}{1} = 3 \text{ days} \] ### Final Answer B and C can complete the remaining work in **3 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then, the total number of days needed for the completion of the work is

A,B andC can do a job working alone in 12, 16 and 24 days, respectively.In how many days, they can do the job, if they worked together?

A and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?

A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A, B and C can complete a work in 8, 16 and 24 days respectively. The...

    Text Solution

    |

  2. A, B and C can do a job working alone in 50, 75 and 20 days respective...

    Text Solution

    |

  3. A, B and C can do job in 9, 12 and 36 days respectively if they worked...

    Text Solution

    |

  4. If A, B and C can do a job working alone in 12, 18 and 36 days respect...

    Text Solution

    |

  5. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  6. Ramesh and Rahman can do a work in 20 and 25 days respectively. After ...

    Text Solution

    |

  7. A can do a piece of work in 10 days and B can do it in 12 days. They w...

    Text Solution

    |

  8. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  9. A and B can do a piece of work in 30 and 36 days respectively. They b...

    Text Solution

    |

  10. A, B and C can do a work separately in 16, 32 and 48 days respectivel...

    Text Solution

    |

  11. Anushka and Anirudh working together can complete a piece of work in 2...

    Text Solution

    |

  12. The working capacity of A is 50% more than that of B. If A can comple...

    Text Solution

    |

  13. The ratio of the working capacity of A and B is 3: 5. They can do it i...

    Text Solution

    |

  14. Babu and Asha can do together a work in 7 days. Asha is 1(3)/(4) time...

    Text Solution

    |

  15. The ratio of the working capacity of A and B is 2:3. A takes 10 days ...

    Text Solution

    |

  16. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |

  17. A is thrice as good a workman as B. C alone takes 48 days to paint a h...

    Text Solution

    |

  18. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |

  19. A,B and C together can finish a task in 7.5 days. C is thrice as produ...

    Text Solution

    |

  20. A is thrice as productive as C. Together they can complete a job in 22...

    Text Solution

    |