Home
Class 14
MATHS
A can do a piece of work in 10 days and ...

A can do a piece of work in 10 days and B can do it in 12 days. They work together for 3 days. Then B leaves and A alone continues. 2 days after that C joins and the work is completed in 2 days more. In how many days can C do it, if he works alone ?

A

40 days

B

50 days

C

40 days

D

60 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Determine the work efficiencies of A and B - A can complete the work in 10 days, so A's efficiency is: \[ \text{Efficiency of A} = \frac{1 \text{ work}}{10 \text{ days}} = \frac{1}{10} \text{ work/day} \] - B can complete the work in 12 days, so B's efficiency is: \[ \text{Efficiency of B} = \frac{1 \text{ work}}{12 \text{ days}} = \frac{1}{12} \text{ work/day} \] ### Step 2: Calculate the combined efficiency of A and B - The combined efficiency of A and B is: \[ \text{Combined Efficiency} = \frac{1}{10} + \frac{1}{12} \] - To add these fractions, find a common denominator (which is 60): \[ \text{Combined Efficiency} = \frac{6}{60} + \frac{5}{60} = \frac{11}{60} \text{ work/day} \] ### Step 3: Calculate the work done by A and B in 3 days - The amount of work done by A and B together in 3 days is: \[ \text{Work done in 3 days} = 3 \times \frac{11}{60} = \frac{33}{60} = \frac{11}{20} \text{ of the work} \] ### Step 4: Determine the remaining work - The total work is 1 (or 60 units if we consider the total work as 60 units). Thus, the remaining work after 3 days is: \[ \text{Remaining Work} = 1 - \frac{11}{20} = \frac{9}{20} \text{ of the work} \] ### Step 5: Calculate the work done by A alone in the next 2 days - A continues to work alone for 2 days. The work done by A in 2 days is: \[ \text{Work done by A in 2 days} = 2 \times \frac{1}{10} = \frac{2}{10} = \frac{1}{5} \text{ of the work} \] ### Step 6: Determine the remaining work after A's 2 days - The remaining work after A works for 2 days is: \[ \text{Remaining Work} = \frac{9}{20} - \frac{1}{5} = \frac{9}{20} - \frac{4}{20} = \frac{5}{20} = \frac{1}{4} \text{ of the work} \] ### Step 7: Calculate the time taken by A and C together to finish the remaining work - A's efficiency is \(\frac{1}{10}\) and let C's efficiency be \(c\). Together, their efficiency is: \[ \text{Efficiency of A and C} = \frac{1}{10} + c \] - They complete the remaining \(\frac{1}{4}\) of the work in 2 days: \[ 2 \left(\frac{1}{10} + c\right) = \frac{1}{4} \] Simplifying gives: \[ \frac{1}{10} + c = \frac{1}{8} \] \[ c = \frac{1}{8} - \frac{1}{10} \] Finding a common denominator (40): \[ c = \frac{5}{40} - \frac{4}{40} = \frac{1}{40} \text{ work/day} \] ### Step 8: Calculate the number of days C would take to complete the work alone - If C's efficiency is \(\frac{1}{40}\), then the time taken by C to complete the entire work alone is: \[ \text{Time taken by C} = \frac{1 \text{ work}}{\frac{1}{40} \text{ work/day}} = 40 \text{ days} \] Thus, C can complete the work alone in **40 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 120 days and B can do it in 150 days.The work together for 20 days.Then,B leave and A alone continues the work.12 days after that C joins A and the work.is completed in 48 days more.In how many days can C do it,if he works alone?

A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in

A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?

A alone can do a piece of work in 10 days and B alone can do it in 15 days. In how many days will A and B together do the same work?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A can do a work in 21 days and B in 42 days. If they work on it toget...

    Text Solution

    |

  2. Ramesh and Rahman can do a work in 20 and 25 days respectively. After ...

    Text Solution

    |

  3. A can do a piece of work in 10 days and B can do it in 12 days. They w...

    Text Solution

    |

  4. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  5. A and B can do a piece of work in 30 and 36 days respectively. They b...

    Text Solution

    |

  6. A, B and C can do a work separately in 16, 32 and 48 days respectivel...

    Text Solution

    |

  7. Anushka and Anirudh working together can complete a piece of work in 2...

    Text Solution

    |

  8. The working capacity of A is 50% more than that of B. If A can comple...

    Text Solution

    |

  9. The ratio of the working capacity of A and B is 3: 5. They can do it i...

    Text Solution

    |

  10. Babu and Asha can do together a work in 7 days. Asha is 1(3)/(4) time...

    Text Solution

    |

  11. The ratio of the working capacity of A and B is 2:3. A takes 10 days ...

    Text Solution

    |

  12. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |

  13. A is thrice as good a workman as B. C alone takes 48 days to paint a h...

    Text Solution

    |

  14. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |

  15. A,B and C together can finish a task in 7.5 days. C is thrice as produ...

    Text Solution

    |

  16. A is thrice as productive as C. Together they can complete a job in 22...

    Text Solution

    |

  17. A, B and C together can finish a task in 12 days. A is twice as produ...

    Text Solution

    |

  18. P, Q, R are 3 typists working simultaneously, can type 216 pages in 4...

    Text Solution

    |

  19. B works three times more slowly than A and C together. C can do it twi...

    Text Solution

    |

  20. Three persons undertake to complete a piece of work for ₹ 1,200. The ...

    Text Solution

    |