Home
Class 14
MATHS
A, B and C can do a work separately in 1...

A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?

A

10 days

B

9 days

C

12 days

D

14 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will follow these steps: ### Step 1: Calculate the work done by A, B, and C individually. - A can complete the work in 16 days, so A's work rate (efficiency) is \( \frac{1}{16} \) of the work per day. - B can complete the work in 32 days, so B's work rate (efficiency) is \( \frac{1}{32} \) of the work per day. - C can complete the work in 48 days, so C's work rate (efficiency) is \( \frac{1}{48} \) of the work per day. ### Step 2: Find the LCM of the days to determine the total work. - The LCM of 16, 32, and 48 is 96. This means the total work can be considered as 96 units. ### Step 3: Calculate the efficiencies in terms of the total work. - A's efficiency = \( \frac{96}{16} = 6 \) units/day - B's efficiency = \( \frac{96}{32} = 3 \) units/day - C's efficiency = \( \frac{96}{48} = 2 \) units/day ### Step 4: Determine the total efficiency when all three work together. - Total efficiency = A's efficiency + B's efficiency + C's efficiency = \( 6 + 3 + 2 = 11 \) units/day. ### Step 5: Calculate the work done by B and C when they leave early. - B leaves 8 days before the work is completed. Therefore, the work done by B in those 8 days = \( 8 \times 3 = 24 \) units. - C leaves 6 days before the work is completed. Therefore, the work done by C in those 6 days = \( 6 \times 2 = 12 \) units. ### Step 6: Calculate the total work done by A, B, and C. - If B and C had not left early, the total work done by A, B, and C together over the entire period would be: - Total work = Work done by A + Work done by B + Work done by C - Work done by A in the full time = \( 12 \times 6 = 72 \) units (since they work together for 12 days). - Total work = \( 72 + 24 + 12 = 108 \) units. ### Step 7: Calculate the total work done with the adjustments. - Since B and C leave early, the total work done is \( 96 \) units (the total work). - The total work done by A, B, and C together is \( 96 \) units, but we need to account for the work done by B and C before they left. - The total work done = \( 72 + 24 + 12 = 108 \) units, but since the total work is only 96 units, we need to find the time taken to complete the work. ### Step 8: Calculate the time taken to finish the work. - The total work done is 96 units, and the combined efficiency is 11 units/day. - The time taken to finish the work = \( \frac{96 \text{ units}}{11 \text{ units/day}} \approx 8.73 \) days. ### Conclusion: The work is finished in approximately 12 days. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A, B and C can do a work in 8, 16 and 24 days respectively. They all begin together. A continues to work till it is finished, C leaving off 2 days and B one day before its completion. In what time is the work finished?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A,B and C can do a piece of work in 15,12 and 20 days respectively.They started the work together,but C left after 2 days.In how many days will the remaining work be completed by A and B?

A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:

A, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continously till it is finished , C leaves the work 2 days before its completion and B leaves the work 1 day before its completion . In what time is the work finished ?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. P and Q together can do a job in 6 days. Q and R can finish the same j...

    Text Solution

    |

  2. A and B can do a piece of work in 30 and 36 days respectively. They b...

    Text Solution

    |

  3. A, B and C can do a work separately in 16, 32 and 48 days respectivel...

    Text Solution

    |

  4. Anushka and Anirudh working together can complete a piece of work in 2...

    Text Solution

    |

  5. The working capacity of A is 50% more than that of B. If A can comple...

    Text Solution

    |

  6. The ratio of the working capacity of A and B is 3: 5. They can do it i...

    Text Solution

    |

  7. Babu and Asha can do together a work in 7 days. Asha is 1(3)/(4) time...

    Text Solution

    |

  8. The ratio of the working capacity of A and B is 2:3. A takes 10 days ...

    Text Solution

    |

  9. A does half as much work as B in three fourth of the times. If togethe...

    Text Solution

    |

  10. A is thrice as good a workman as B. C alone takes 48 days to paint a h...

    Text Solution

    |

  11. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |

  12. A,B and C together can finish a task in 7.5 days. C is thrice as produ...

    Text Solution

    |

  13. A is thrice as productive as C. Together they can complete a job in 22...

    Text Solution

    |

  14. A, B and C together can finish a task in 12 days. A is twice as produ...

    Text Solution

    |

  15. P, Q, R are 3 typists working simultaneously, can type 216 pages in 4...

    Text Solution

    |

  16. B works three times more slowly than A and C together. C can do it twi...

    Text Solution

    |

  17. Three persons undertake to complete a piece of work for ₹ 1,200. The ...

    Text Solution

    |

  18. A and B separately can complete a work in 18 days and 24 days respecti...

    Text Solution

    |

  19. A and B together complete 11/19 part of the work. In the same time B a...

    Text Solution

    |

  20. A skilled, a half skilled and an unskilled labour work for 7, 8 and 10...

    Text Solution

    |