Home
Class 14
MATHS
A is thrice as productive as C. Together...

A is thrice as productive as C. Together they can complete a job in 22.5 days. If B joins them after they have worked for 15 days then in how many days can they finish the rest of the job if B alone can do the job in 15 days?

A

6

B

3

C

9

D

2

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the efficiencies of A, B, and C, and then calculate how much work they can complete together. ### Step 1: Determine the efficiencies of A, B, and C Given that A is thrice as productive as C, we can denote the efficiency of C as \( x \). Therefore, the efficiency of A will be \( 3x \). Now, the combined efficiency of A and C is: \[ \text{Efficiency of A and C} = A + C = 3x + x = 4x \] We know that A and C can complete the job in 22.5 days. Thus, their combined work rate (efficiency) can be calculated as: \[ \text{Total work} = \text{Efficiency} \times \text{Time} \] Let’s denote the total work as \( W \). Therefore: \[ W = 4x \times 22.5 \] ### Step 2: Calculate the total work (W) To find \( W \), we can express it in terms of \( x \): \[ W = 4x \times 22.5 = 90x \] ### Step 3: Determine the efficiency of B B can complete the job alone in 15 days. Thus, B's efficiency is: \[ \text{Efficiency of B} = \frac{W}{15} = \frac{90x}{15} = 6x \] ### Step 4: Calculate the work done by A and C in 15 days Now, we need to find out how much work A and C can complete in 15 days: \[ \text{Work done by A and C in 15 days} = \text{Efficiency of A and C} \times \text{Time} = 4x \times 15 = 60x \] ### Step 5: Calculate the remaining work Now, we can find the remaining work after A and C have worked for 15 days: \[ \text{Remaining work} = W - \text{Work done by A and C} = 90x - 60x = 30x \] ### Step 6: Calculate the combined efficiency of A, B, and C When B joins A and C, their combined efficiency becomes: \[ \text{Combined efficiency of A, B, and C} = 4x + 6x = 10x \] ### Step 7: Calculate the time taken to finish the remaining work Now, we need to find out how many days it will take for A, B, and C to finish the remaining work of \( 30x \): \[ \text{Time} = \frac{\text{Remaining work}}{\text{Combined efficiency}} = \frac{30x}{10x} = 3 \text{ days} \] ### Conclusion Thus, A, B, and C can finish the remaining work in **3 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?

A can do 75% of a job in 9 days and B can do half of the job in 8 days. If they work on it together, then in how many days can they do half of the job?

A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in

A can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. C is 5 times as productive as B. A takes 60 days to complete a task. ...

    Text Solution

    |

  2. A,B and C together can finish a task in 7.5 days. C is thrice as produ...

    Text Solution

    |

  3. A is thrice as productive as C. Together they can complete a job in 22...

    Text Solution

    |

  4. A, B and C together can finish a task in 12 days. A is twice as produ...

    Text Solution

    |

  5. P, Q, R are 3 typists working simultaneously, can type 216 pages in 4...

    Text Solution

    |

  6. B works three times more slowly than A and C together. C can do it twi...

    Text Solution

    |

  7. Three persons undertake to complete a piece of work for ₹ 1,200. The ...

    Text Solution

    |

  8. A and B separately can complete a work in 18 days and 24 days respecti...

    Text Solution

    |

  9. A and B together complete 11/19 part of the work. In the same time B a...

    Text Solution

    |

  10. A skilled, a half skilled and an unskilled labour work for 7, 8 and 10...

    Text Solution

    |

  11. Working alone A can do the task in 27 hours and B can do it in 54 hour...

    Text Solution

    |

  12. If A had worked alone he would have taken 63 hours to do the task. Wha...

    Text Solution

    |

  13. The labourers A, B, C were given a contract of Rs.750 for doing a cer...

    Text Solution

    |

  14. The daily wages of A and B respectively are ₹.3.50 and 2.50. When A fi...

    Text Solution

    |

  15. A & B jointly made a profit of Rs.1650 and they decided to share it su...

    Text Solution

    |

  16. If a man earns ₹ 2,000 for his first 50 hours of work in a week and t...

    Text Solution

    |

  17. One man can do as much work in one day as a woman can do in 2 days. A ...

    Text Solution

    |

  18. A labourer was appointed by a contractor on the condition he would be ...

    Text Solution

    |

  19. If A, B and C together do a job in 4 days, A and C together do the job...

    Text Solution

    |

  20. Working together A, B and C can complete a task in 12 days. A and B ca...

    Text Solution

    |