Home
Class 14
MATHS
B works three times more slowly than A a...

B works three times more slowly than A and C together. C can do it twice slowly than A and B. if they work together, the work is completed in 10 days. In how many days they will do it separately?

A

24, 40, 30

B

40, 30, 24

C

40,24, 20

D

30, 20, 40

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will define the efficiencies of A, B, and C based on the information given and then calculate the time taken by each to complete the work separately. ### Step 1: Define the relationship between A, B, and C - Let the efficiency of A be \( a \) (units of work per day). - According to the problem, B works three times more slowly than A and C together. Therefore, if A and C together can do \( a + c \) work, then B's efficiency can be expressed as: \[ b = \frac{1}{3}(a + c) \] ### Step 2: Define C's efficiency - The problem states that C works twice as slowly as A and B together. Therefore, if A and B together can do \( a + b \) work, then C's efficiency can be expressed as: \[ c = \frac{1}{2}(a + b) \] ### Step 3: Express B's efficiency in terms of A and C - From the equation for B, we can substitute \( c \) from the previous step: \[ b = \frac{1}{3}(a + \frac{1}{2}(a + b)) \] Simplifying this gives: \[ b = \frac{1}{3}(a + \frac{1}{2}a + \frac{1}{2}b) = \frac{1}{3}(\frac{3}{2}a + \frac{1}{2}b) \] Multiplying through by 3 to eliminate the fraction: \[ 3b = \frac{3}{2}a + \frac{1}{2}b \] Rearranging gives: \[ \frac{5}{2}b = \frac{3}{2}a \implies b = \frac{3}{5}a \] ### Step 4: Substitute B's efficiency back into C's equation - Now substituting \( b \) back into C's equation: \[ c = \frac{1}{2}(a + \frac{3}{5}a) = \frac{1}{2}(\frac{8}{5}a) = \frac{4}{5}a \] ### Step 5: Calculate total efficiency - Now we have: - \( a \) (efficiency of A) - \( b = \frac{3}{5}a \) (efficiency of B) - \( c = \frac{4}{5}a \) (efficiency of C) - The total efficiency of A, B, and C together is: \[ a + b + c = a + \frac{3}{5}a + \frac{4}{5}a = a + \frac{7}{5}a = \frac{12}{5}a \] ### Step 6: Work done in 10 days - According to the problem, A, B, and C together complete the work in 10 days. Therefore, the total work done is: \[ \text{Total Work} = \text{Total Efficiency} \times \text{Time} = \frac{12}{5}a \times 10 = 24a \] ### Step 7: Calculate individual times - Now we can find the time taken by each to complete the work separately: - Time taken by A: \[ \text{Time}_A = \frac{\text{Total Work}}{\text{Efficiency of A}} = \frac{24a}{a} = 24 \text{ days} \] - Time taken by B: \[ \text{Time}_B = \frac{24a}{\frac{3}{5}a} = 24 \times \frac{5}{3} = 40 \text{ days} \] - Time taken by C: \[ \text{Time}_C = \frac{24a}{\frac{4}{5}a} = 24 \times \frac{5}{4} = 30 \text{ days} \] ### Final Answer - Therefore, the time taken by A, B, and C to complete the work separately is: - A: 24 days - B: 40 days - C: 30 days
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?

A can do a work in 36 days and B in 12 days. If they work on it together, then in how many days will they be able to do the work?

A takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?

A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in :

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A, B and C together can finish a task in 12 days. A is twice as produ...

    Text Solution

    |

  2. P, Q, R are 3 typists working simultaneously, can type 216 pages in 4...

    Text Solution

    |

  3. B works three times more slowly than A and C together. C can do it twi...

    Text Solution

    |

  4. Three persons undertake to complete a piece of work for ₹ 1,200. The ...

    Text Solution

    |

  5. A and B separately can complete a work in 18 days and 24 days respecti...

    Text Solution

    |

  6. A and B together complete 11/19 part of the work. In the same time B a...

    Text Solution

    |

  7. A skilled, a half skilled and an unskilled labour work for 7, 8 and 10...

    Text Solution

    |

  8. Working alone A can do the task in 27 hours and B can do it in 54 hour...

    Text Solution

    |

  9. If A had worked alone he would have taken 63 hours to do the task. Wha...

    Text Solution

    |

  10. The labourers A, B, C were given a contract of Rs.750 for doing a cer...

    Text Solution

    |

  11. The daily wages of A and B respectively are ₹.3.50 and 2.50. When A fi...

    Text Solution

    |

  12. A & B jointly made a profit of Rs.1650 and they decided to share it su...

    Text Solution

    |

  13. If a man earns ₹ 2,000 for his first 50 hours of work in a week and t...

    Text Solution

    |

  14. One man can do as much work in one day as a woman can do in 2 days. A ...

    Text Solution

    |

  15. A labourer was appointed by a contractor on the condition he would be ...

    Text Solution

    |

  16. If A, B and C together do a job in 4 days, A and C together do the job...

    Text Solution

    |

  17. Working together A, B and C can complete a task in 12 days. A and B ca...

    Text Solution

    |

  18. B would have taken 10 hours more than what A would have taken to compl...

    Text Solution

    |

  19. If x can finish a job in 4 hours and y can finish the same job in 8 ho...

    Text Solution

    |

  20. x does (1)/(4) of a job in 6 days, y completes rest of the job in 12...

    Text Solution

    |