Home
Class 14
MATHS
A company has a job to prepare certain n...

A company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?

A

4/3 days

B

3 days

C

3 days

D

12 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem of how many days the company will take to complete the job if all machines A, B, and C are used simultaneously, we can follow these steps: ### Step 1: Determine the work done by each machine in one day. - Machine A can complete the job in 3 days. Therefore, the work done by A in one day is: \[ \text{Work by A in one day} = \frac{1}{3} \text{ of the job} \] - Machine B can complete the job in 4 days. Therefore, the work done by B in one day is: \[ \text{Work by B in one day} = \frac{1}{4} \text{ of the job} \] - Machine C can complete the job in 6 days. Therefore, the work done by C in one day is: \[ \text{Work by C in one day} = \frac{1}{6} \text{ of the job} \] ### Step 2: Calculate the total work done by all machines in one day. To find the total work done by all machines in one day, we add the work done by each machine: \[ \text{Total work in one day} = \text{Work by A} + \text{Work by B} + \text{Work by C} \] \[ = \frac{1}{3} + \frac{1}{4} + \frac{1}{6} \] ### Step 3: Find a common denominator and add the fractions. The least common multiple (LCM) of 3, 4, and 6 is 12. We convert each fraction: \[ \frac{1}{3} = \frac{4}{12}, \quad \frac{1}{4} = \frac{3}{12}, \quad \frac{1}{6} = \frac{2}{12} \] Now, add them together: \[ \text{Total work in one day} = \frac{4}{12} + \frac{3}{12} + \frac{2}{12} = \frac{4 + 3 + 2}{12} = \frac{9}{12} = \frac{3}{4} \text{ of the job} \] ### Step 4: Calculate the time taken to complete the job. If the machines together complete \(\frac{3}{4}\) of the job in one day, then the time taken to complete the entire job (1 job) is: \[ \text{Time} = \frac{1 \text{ job}}{\frac{3}{4} \text{ job/day}} = \frac{4}{3} \text{ days} \] ### Final Answer: The company will take \(\frac{4}{3}\) days to complete the job if all machines are used simultaneously. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A company has a job to prepare certain no. of cans and there are three machines A, B & C for this job. A can complete the job in 3 days, B can complete the job in 4 days and C can complete the job in 6 days. How many days the company will take to complete job if all the machines are used simultaneously? A)4 days B)4/3 days C)3 days D)12 days

22 men can complete a job in 16days. In how many days, will 32 men complete that job?

5 men can complete a job in 8 days. How many days will it take if 12 men do the job?

X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in

A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?

P can do a job in 12 days and Q can do the same job in 6 days, in how many days working together they can complete the job?

A can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?

X can complete a job in 12 days. If X and Y work together, they can complete the job in 6(2/3) days. 'Y' alone can complete the job on

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. Three machines, A, B and C can be used to produce a product. Machine A...

    Text Solution

    |

  2. Two typists undertake to do a job. The second typist begins working on...

    Text Solution

    |

  3. A company has a job to prepare certain number cans and there are three...

    Text Solution

    |

  4. A can complete a piece of work in 4 days. B takes double the time tak...

    Text Solution

    |

  5. There's a lot of work in preparing a birthday dinner. Even after the t...

    Text Solution

    |

  6. It takes six technicians a total of 10 hr to build a new server from ...

    Text Solution

    |

  7. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  8. A alone takes 4 more days to complete a work, in that time A and B can...

    Text Solution

    |

  9. 3 typists P, Q and R type some pages. The first two typists P and Q, w...

    Text Solution

    |

  10. If 12 carpenters working 6 hours a day can make 460 chairs in 240 days...

    Text Solution

    |

  11. The expenditure on gas is ₹ 450. If 6 burners light for 8 days for 6 h...

    Text Solution

    |

  12. 40 persons can do a work in 15 days if they work 8 hours per day, then...

    Text Solution

    |

  13. 38 men can complete a work by working 6 Hrs per day in 12 days then ca...

    Text Solution

    |

  14. 6 persons earn ₹ 8,400 in a week, if they work 8 hours per day then ho...

    Text Solution

    |

  15. 30 persons can complete a work in 10 days. If they work 4 hours per da...

    Text Solution

    |

  16. A certain number of persons can complete a piece of work in 55 days. I...

    Text Solution

    |

  17. A group of persons can do a work in 10 days. If 5 persons remains abse...

    Text Solution

    |

  18. 40 people can complete a work in 40 days. They started the work togeth...

    Text Solution

    |

  19. 50 people can complete a work in 50 days. They started the work togeth...

    Text Solution

    |

  20. 40 men can do a piece of work in 20 days. After how many days 8 men le...

    Text Solution

    |