Home
Class 14
MATHS
A can complete a piece of work in 4 days...

A can complete a piece of work in 4 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. They are paired in groups of two each. One pair takes two-thirds the time needed by the second pair to complete the work. Which is the first pair?

A

A and B

B

A and C

C

B and C

D

A and D

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the time taken by each individual (A, B, C, and D) to complete the work, then calculate their efficiencies, and finally analyze the pairs to find which one is the first pair. ### Step 1: Determine the time taken by each worker - A can complete the work in 4 days. - B takes double the time of A: \[ \text{Time taken by B} = 2 \times 4 = 8 \text{ days} \] - C takes double the time of B: \[ \text{Time taken by C} = 2 \times 8 = 16 \text{ days} \] - D takes double the time of C: \[ \text{Time taken by D} = 2 \times 16 = 32 \text{ days} \] ### Step 2: Calculate the work done by each worker in one day - A's work rate (efficiency) = \( \frac{1}{4} \) (since A completes the work in 4 days) - B's work rate = \( \frac{1}{8} \) - C's work rate = \( \frac{1}{16} \) - D's work rate = \( \frac{1}{32} \) ### Step 3: Calculate the combined efficiency of each pair 1. **Pair A and B**: \[ \text{Efficiency of A and B} = \frac{1}{4} + \frac{1}{8} = \frac{2}{8} + \frac{1}{8} = \frac{3}{8} \] Time taken by A and B to complete the work: \[ \text{Time} = \frac{1}{\frac{3}{8}} = \frac{8}{3} \text{ days} \] 2. **Pair C and D**: \[ \text{Efficiency of C and D} = \frac{1}{16} + \frac{1}{32} = \frac{2}{32} + \frac{1}{32} = \frac{3}{32} \] Time taken by C and D to complete the work: \[ \text{Time} = \frac{1}{\frac{3}{32}} = \frac{32}{3} \text{ days} \] 3. **Pair B and C**: \[ \text{Efficiency of B and C} = \frac{1}{8} + \frac{1}{16} = \frac{2}{16} + \frac{1}{16} = \frac{3}{16} \] Time taken by B and C to complete the work: \[ \text{Time} = \frac{1}{\frac{3}{16}} = \frac{16}{3} \text{ days} \] 4. **Pair A and D**: \[ \text{Efficiency of A and D} = \frac{1}{4} + \frac{1}{32} = \frac{8}{32} + \frac{1}{32} = \frac{9}{32} \] Time taken by A and D to complete the work: \[ \text{Time} = \frac{1}{\frac{9}{32}} = \frac{32}{9} \text{ days} \] ### Step 4: Compare the pairs based on the time taken According to the problem, one pair takes two-thirds the time needed by the second pair. We will check each pair against the others: - **Comparing A and B with C and D**: \[ \frac{8/3}{32/3} = \frac{8}{32} = \frac{1}{4} \quad \text{(not two-thirds)} \] - **Comparing B and C with A and D**: \[ \frac{16/3}{32/9} = \frac{16 \times 9}{32 \times 3} = \frac{144}{96} = \frac{3}{2} \quad \text{(not two-thirds)} \] - **Comparing A and D with C and D**: \[ \frac{32/9}{32/3} = \frac{32 \times 3}{32 \times 9} = \frac{3}{9} = \frac{1}{3} \quad \text{(not two-thirds)} \] - **Comparing A and B with B and C**: \[ \frac{8/3}{16/3} = \frac{8}{16} = \frac{1}{2} \quad \text{(not two-thirds)} \] ### Conclusion After checking all pairs, we find that the first pair that satisfies the condition of taking two-thirds the time of the second pair is **A and B**. ### Final Answer The first pair is **A and B**.
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is

A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?

A can do a piece of work in 6 days. B takes 8 days and Ctakes as long as A and B would take working together. B and C working together will complete the work in

A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. Two typists undertake to do a job. The second typist begins working on...

    Text Solution

    |

  2. A company has a job to prepare certain number cans and there are three...

    Text Solution

    |

  3. A can complete a piece of work in 4 days. B takes double the time tak...

    Text Solution

    |

  4. There's a lot of work in preparing a birthday dinner. Even after the t...

    Text Solution

    |

  5. It takes six technicians a total of 10 hr to build a new server from ...

    Text Solution

    |

  6. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  7. A alone takes 4 more days to complete a work, in that time A and B can...

    Text Solution

    |

  8. 3 typists P, Q and R type some pages. The first two typists P and Q, w...

    Text Solution

    |

  9. If 12 carpenters working 6 hours a day can make 460 chairs in 240 days...

    Text Solution

    |

  10. The expenditure on gas is ₹ 450. If 6 burners light for 8 days for 6 h...

    Text Solution

    |

  11. 40 persons can do a work in 15 days if they work 8 hours per day, then...

    Text Solution

    |

  12. 38 men can complete a work by working 6 Hrs per day in 12 days then ca...

    Text Solution

    |

  13. 6 persons earn ₹ 8,400 in a week, if they work 8 hours per day then ho...

    Text Solution

    |

  14. 30 persons can complete a work in 10 days. If they work 4 hours per da...

    Text Solution

    |

  15. A certain number of persons can complete a piece of work in 55 days. I...

    Text Solution

    |

  16. A group of persons can do a work in 10 days. If 5 persons remains abse...

    Text Solution

    |

  17. 40 people can complete a work in 40 days. They started the work togeth...

    Text Solution

    |

  18. 50 people can complete a work in 50 days. They started the work togeth...

    Text Solution

    |

  19. 40 men can do a piece of work in 20 days. After how many days 8 men le...

    Text Solution

    |

  20. A contractor wants to complete a project in 90 days and he employed 60...

    Text Solution

    |