Home
Class 14
MATHS
A alone takes 4 more days to complete a ...

A alone takes 4 more days to complete a work, in that time A and B can complete it together and B alone takes 16 more days to complete the same. In how many days they will do it together?

A

1. 6

B

2. 8

C

3. 12

D

4. 10

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will define the variables and use the information given in the question. ### Step 1: Define Variables Let: - \( x \) = the number of days A takes to complete the work alone. - \( y \) = the number of days B takes to complete the work alone. From the problem, we know: - A takes 4 more days than the time they take together: \( x = t + 4 \) - B takes 16 more days than the time they take together: \( y = t + 16 \) ### Step 2: Set Up the Equation When A and B work together, their combined work rate is the sum of their individual work rates. The work rate can be expressed as: - A's work rate = \( \frac{1}{x} \) - B's work rate = \( \frac{1}{y} \) Thus, their combined work rate when working together is: \[ \frac{1}{x} + \frac{1}{y} = \frac{1}{t} \] ### Step 3: Substitute the Values of \( x \) and \( y \) Substituting \( x \) and \( y \) in terms of \( t \): \[ \frac{1}{t + 4} + \frac{1}{t + 16} = \frac{1}{t} \] ### Step 4: Find a Common Denominator To solve this equation, we can find a common denominator for the left side: \[ \frac{(t + 16) + (t + 4)}{(t + 4)(t + 16)} = \frac{1}{t} \] This simplifies to: \[ \frac{2t + 20}{(t + 4)(t + 16)} = \frac{1}{t} \] ### Step 5: Cross-Multiply Cross-multiplying gives: \[ (2t + 20)t = (t + 4)(t + 16) \] ### Step 6: Expand Both Sides Expanding both sides: \[ 2t^2 + 20t = t^2 + 20t + 64 \] ### Step 7: Rearrange the Equation Rearranging gives: \[ 2t^2 + 20t - t^2 - 20t - 64 = 0 \] This simplifies to: \[ t^2 - 64 = 0 \] ### Step 8: Solve for \( t \) Factoring gives: \[ (t - 8)(t + 8) = 0 \] Thus, \( t = 8 \) (since time cannot be negative). ### Step 9: Conclusion The time taken by A and B together to complete the work is \( t = 8 \) days.
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. It takes six technicians a total of 10 hr to build a new server from ...

    Text Solution

    |

  2. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  3. A alone takes 4 more days to complete a work, in that time A and B can...

    Text Solution

    |

  4. 3 typists P, Q and R type some pages. The first two typists P and Q, w...

    Text Solution

    |

  5. If 12 carpenters working 6 hours a day can make 460 chairs in 240 days...

    Text Solution

    |

  6. The expenditure on gas is ₹ 450. If 6 burners light for 8 days for 6 h...

    Text Solution

    |

  7. 40 persons can do a work in 15 days if they work 8 hours per day, then...

    Text Solution

    |

  8. 38 men can complete a work by working 6 Hrs per day in 12 days then ca...

    Text Solution

    |

  9. 6 persons earn ₹ 8,400 in a week, if they work 8 hours per day then ho...

    Text Solution

    |

  10. 30 persons can complete a work in 10 days. If they work 4 hours per da...

    Text Solution

    |

  11. A certain number of persons can complete a piece of work in 55 days. I...

    Text Solution

    |

  12. A group of persons can do a work in 10 days. If 5 persons remains abse...

    Text Solution

    |

  13. 40 people can complete a work in 40 days. They started the work togeth...

    Text Solution

    |

  14. 50 people can complete a work in 50 days. They started the work togeth...

    Text Solution

    |

  15. 40 men can do a piece of work in 20 days. After how many days 8 men le...

    Text Solution

    |

  16. A contractor wants to complete a project in 90 days and he employed 60...

    Text Solution

    |

  17. A contractor undertakes to do a piece of work in 40 days. He engages 1...

    Text Solution

    |

  18. 150 workers were engaged to finish a piece of work in a certain number...

    Text Solution

    |

  19. A canal of a village can be cleaned by 24 villagers in 12 days. The nu...

    Text Solution

    |

  20. Working 7 hours in a day, 4 men can do a piece of work in 8 days. Work...

    Text Solution

    |