38 men can complete a work by working 6 ...

38 men can complete a work by working 6 Hrs per day in 12 days then calculate in how many days 51 men can do double of the work by work ing 8 hrs per day?

A

56 days

B

`(228)/(17)` days

C

14 days

D

`(128)/(17)` days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will follow these steps: ### Step 1: Calculate the total work done by 38 men in 12 days working 6 hours a day. Total work (W) can be calculated using the formula: \[ W = \text{Number of Men} \times \text{Hours per Day} \times \text{Number of Days} \] Here, we have: - Number of Men (M1) = 38 - Hours per Day (H1) = 6 - Number of Days (D1) = 12 So, \[ W = 38 \times 6 \times 12 \] ### Step 2: Calculate the total work. Calculating the total work: \[ W = 38 \times 6 = 228 \] \[ W = 228 \times 12 = 2736 \text{ hours} \] ### Step 3: Since we need to find out how many days 51 men can do double the work, we first calculate double the work. Double the work (W2) is: \[ W2 = 2 \times W = 2 \times 2736 = 5472 \text{ hours} \] ### Step 4: Calculate how many days it will take for 51 men working 8 hours a day to complete double the work. Using the formula for work again: \[ W2 = \text{Number of Men} \times \text{Hours per Day} \times \text{Number of Days} \] Let D2 be the number of days required. We have: - Number of Men (M2) = 51 - Hours per Day (H2) = 8 So, \[ 5472 = 51 \times 8 \times D2 \] ### Step 5: Rearranging the equation to find D2. Rearranging gives us: \[ D2 = \frac{5472}{51 \times 8} \] ### Step 6: Calculate the value of D2. Calculating the denominator: \[ 51 \times 8 = 408 \] Now substituting back: \[ D2 = \frac{5472}{408} \] ### Step 7: Simplifying the fraction. Calculating: \[ D2 = 13.4 \text{ days} \] ### Final Answer: Thus, it will take approximately 13.4 days for 51 men to complete double the work working 8 hours a day. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?

If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?

If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?

If 30 men working 9 h per day can reap a field in 16 days, in how many days, will 36 men reap the field working 8 h per day ?

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

If 12 men or 18 women can do a work in 14 days,then in how many days will 8 men and 16 women do the same work?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. The expenditure on gas is ₹ 450. If 6 burners light for 8 days for 6 h...

    Text Solution

    |

  2. 40 persons can do a work in 15 days if they work 8 hours per day, then...

    Text Solution

    |

  3. 38 men can complete a work by working 6 Hrs per day in 12 days then ca...

    Text Solution

    |

  4. 6 persons earn ₹ 8,400 in a week, if they work 8 hours per day then ho...

    Text Solution

    |

  5. 30 persons can complete a work in 10 days. If they work 4 hours per da...

    Text Solution

    |

  6. A certain number of persons can complete a piece of work in 55 days. I...

    Text Solution

    |

  7. A group of persons can do a work in 10 days. If 5 persons remains abse...

    Text Solution

    |

  8. 40 people can complete a work in 40 days. They started the work togeth...

    Text Solution

    |

  9. 50 people can complete a work in 50 days. They started the work togeth...

    Text Solution

    |

  10. 40 men can do a piece of work in 20 days. After how many days 8 men le...

    Text Solution

    |

  11. A contractor wants to complete a project in 90 days and he employed 60...

    Text Solution

    |

  12. A contractor undertakes to do a piece of work in 40 days. He engages 1...

    Text Solution

    |

  13. 150 workers were engaged to finish a piece of work in a certain number...

    Text Solution

    |

  14. A canal of a village can be cleaned by 24 villagers in 12 days. The nu...

    Text Solution

    |

  15. Working 7 hours in a day, 4 men can do a piece of work in 8 days. Work...

    Text Solution

    |

  16. The ratio of the amount of work done by (x-1) labours in (x+1) days an...

    Text Solution

    |

  17. 35 persons are engaged to complete a work in 60 days. After 32 days it...

    Text Solution

    |

  18. If 90 men can do a certain job in 16 days, working 12 hours day, then ...

    Text Solution

    |

  19. A supply of juice lasts for 35 days. If its use is increased by 40% th...

    Text Solution

    |

  20. A group of workers was put on a job. From the second day onwards, one...

    Text Solution

    |