50 people can complete a work in 50 days...

50 people can complete a work in 50 days. They started the work together but at the end of every 10th day 5 people join the work. In how much time the work would be completed?

A

1. `52(1)/(7)`

B

2. `47(2)/(7)`

C

3. `42(6)/(7)`

D

4. `42(5)/(7)`

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in

A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?

P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed

F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?

The ratio of work efficiency of A & B is 2:5 . If A can complete a work in 10 days. In how many days the work can be completed by B and when they work together , in how many days the work would be completed ?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. A group of persons can do a work in 10 days. If 5 persons remains abse...

    Text Solution

    |

  2. 40 people can complete a work in 40 days. They started the work togeth...

    Text Solution

    |

  3. 50 people can complete a work in 50 days. They started the work togeth...

    Text Solution

    |

  4. 40 men can do a piece of work in 20 days. After how many days 8 men le...

    Text Solution

    |

  5. A contractor wants to complete a project in 90 days and he employed 60...

    Text Solution

    |

  6. A contractor undertakes to do a piece of work in 40 days. He engages 1...

    Text Solution

    |

  7. 150 workers were engaged to finish a piece of work in a certain number...

    Text Solution

    |

  8. A canal of a village can be cleaned by 24 villagers in 12 days. The nu...

    Text Solution

    |

  9. Working 7 hours in a day, 4 men can do a piece of work in 8 days. Work...

    Text Solution

    |

  10. The ratio of the amount of work done by (x-1) labours in (x+1) days an...

    Text Solution

    |

  11. 35 persons are engaged to complete a work in 60 days. After 32 days it...

    Text Solution

    |

  12. If 90 men can do a certain job in 16 days, working 12 hours day, then ...

    Text Solution

    |

  13. A supply of juice lasts for 35 days. If its use is increased by 40% th...

    Text Solution

    |

  14. A group of workers was put on a job. From the second day onwards, one...

    Text Solution

    |

  15. Alord got an order from a garment manufacturer for 480 Denim Shirts. H...

    Text Solution

    |

  16. A group of men decided to do a job in 8 days. But since 10 men dropped...

    Text Solution

    |

  17. A Fort has sufficient food stock for 1500 persons for 50 days. After 1...

    Text Solution

    |

  18. In a camp, 95 men had provisions for 200 days. After 5 days, 30 men le...

    Text Solution

    |

  19. In a camp, 95 men had provisions for 200 days. After 5 days, 30 men le...

    Text Solution

    |

  20. A fort has food stock for 220 soldiers. If a soldier get 45 gram per d...

    Text Solution

    |