Home
Class 14
MATHS
35 persons are engaged to complete a wor...

35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is

A

20

B

35

C

30

D

25

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the total amount of work We know that 35 persons are engaged to complete the work in 60 days. Therefore, the total work can be expressed in terms of "man-days". Total work = Number of persons × Number of days Total work = 35 persons × 60 days = 2100 man-days **Hint:** Remember that "man-days" is a way to express the total work done by a certain number of people over a certain number of days. ### Step 2: Calculate the work done in 32 days After 32 days, it is observed that \( \frac{2}{5} \) of the work has been completed. Work done = \( \frac{2}{5} \) of Total work Work done = \( \frac{2}{5} \) × 2100 man-days = 840 man-days **Hint:** To find the work done, multiply the fraction of work completed by the total work. ### Step 3: Calculate the remaining work To find the remaining work, we subtract the work done from the total work. Remaining work = Total work - Work done Remaining work = 2100 man-days - 840 man-days = 1260 man-days **Hint:** The remaining work is simply the total work minus the work that has already been completed. ### Step 4: Determine the remaining time The total time given for the work is 60 days, and 32 days have already passed. Remaining time = Total time - Time passed Remaining time = 60 days - 32 days = 28 days **Hint:** Subtract the time already spent from the total time to find out how much time is left. ### Step 5: Calculate the number of persons needed to complete the remaining work Now, we need to find out how many persons are required to complete the remaining work in the remaining time. Let \( x \) be the number of persons required. We can set up the equation: Remaining work = Number of persons × Remaining time 1260 man-days = \( x \) persons × 28 days Now, solving for \( x \): \( x = \frac{1260 \text{ man-days}}{28 \text{ days}} \) \( x = 45 \) persons **Hint:** To find the number of persons needed, divide the remaining work by the remaining time. ### Step 6: Calculate the additional persons needed Since there are already 35 persons working, we need to find out how many additional persons are required. Additional persons needed = Total persons required - Persons already working Additional persons needed = 45 persons - 35 persons = 10 persons **Hint:** To find the additional number of persons required, subtract the current number of workers from the total number needed. ### Final Answer The number of persons to be engaged to complete the remaining work in the said period is **10 persons**.
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only (1)/(5)th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

If a person X completes ((1)/(n)) thpart of the work in one day then person X will take n days to complete the work.

If a person X completes a piece of work in n days then work done by person X in one day is ((1)/(n)) part of the work.

If 20 persons can do a piece of work in 7 days then calculate the number of persons required to complete the work in 28 days

If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. Working 7 hours in a day, 4 men can do a piece of work in 8 days. Work...

    Text Solution

    |

  2. The ratio of the amount of work done by (x-1) labours in (x+1) days an...

    Text Solution

    |

  3. 35 persons are engaged to complete a work in 60 days. After 32 days it...

    Text Solution

    |

  4. If 90 men can do a certain job in 16 days, working 12 hours day, then ...

    Text Solution

    |

  5. A supply of juice lasts for 35 days. If its use is increased by 40% th...

    Text Solution

    |

  6. A group of workers was put on a job. From the second day onwards, one...

    Text Solution

    |

  7. Alord got an order from a garment manufacturer for 480 Denim Shirts. H...

    Text Solution

    |

  8. A group of men decided to do a job in 8 days. But since 10 men dropped...

    Text Solution

    |

  9. A Fort has sufficient food stock for 1500 persons for 50 days. After 1...

    Text Solution

    |

  10. In a camp, 95 men had provisions for 200 days. After 5 days, 30 men le...

    Text Solution

    |

  11. In a camp, 95 men had provisions for 200 days. After 5 days, 30 men le...

    Text Solution

    |

  12. A fort has food stock for 220 soldiers. If a soldier get 45 gram per d...

    Text Solution

    |

  13. A garrison of 3300 men had provisions for 32 days, when given at the r...

    Text Solution

    |

  14. Twenty women together complete a piece of work in 16 days, 16 men toge...

    Text Solution

    |

  15. 20 men or 24 women can complete a piece of work in 20 days. If 30 men...

    Text Solution

    |

  16. If 10 men or 20 boys can make 260 mats in 20 days, then how many mats ...

    Text Solution

    |

  17. If 40 men or 60 women or 80 children can do a piece of work in 6 month...

    Text Solution

    |

  18. If 7 men or 10 women can make a 100 meters wall in 10 days, in how man...

    Text Solution

    |

  19. If 7 men or 10 women can make a 100 meters wall in 10 days, in how man...

    Text Solution

    |

  20. If 1 man or 2 women or 3 boys can complete a piece of work in 88 days,...

    Text Solution

    |