Home
Class 14
MATHS
A contractor undertakes to do a piece of...

A contractor undertakes to do a piece of work in 96 days. He engages 100 men at the begin ning. But in the 1/6 of the scheduled time, 1/7 of work is completed. How many additional men should be employed so that the work will be com pleted in time?

A

30

B

20

C

15

D

10

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these calculations: ### Step 1: Determine the total work and the time taken The contractor has undertaken to complete the work in 96 days. We denote the total work as \( W \). ### Step 2: Calculate the time elapsed and work completed In \( \frac{1}{6} \) of the scheduled time: \[ \text{Time elapsed} = \frac{96}{6} = 16 \text{ days} \] In this time, \( \frac{1}{7} \) of the work is completed: \[ \text{Work completed} = \frac{W}{7} \] ### Step 3: Calculate the remaining work The remaining work after 16 days is: \[ \text{Remaining work} = W - \frac{W}{7} = \frac{7W}{7} - \frac{W}{7} = \frac{6W}{7} \] ### Step 4: Determine the remaining time The total time for the project is 96 days, and 16 days have already been used. Thus, the remaining time is: \[ \text{Remaining time} = 96 - 16 = 80 \text{ days} \] ### Step 5: Set up the equation for the remaining work Let \( x \) be the additional number of men needed. The total number of men working now is \( 100 + x \). The work rate for \( 100 + x \) men over the remaining 80 days must equal the remaining work: \[ (100 + x) \times \text{Rate} \times 80 = \frac{6W}{7} \] ### Step 6: Calculate the rate of work The rate of work done by 100 men in 16 days is: \[ 100 \times \text{Rate} \times 16 = \frac{W}{7} \] From this, we can express the rate: \[ \text{Rate} = \frac{W}{7 \times 100 \times 16} = \frac{W}{11200} \] ### Step 7: Substitute the rate into the remaining work equation Substituting the rate back into the equation: \[ (100 + x) \times \frac{W}{11200} \times 80 = \frac{6W}{7} \] ### Step 8: Simplify the equation Cancelling \( W \) from both sides: \[ (100 + x) \times \frac{80}{11200} = \frac{6}{7} \] \[ (100 + x) \times \frac{1}{140} = \frac{6}{7} \] Multiplying both sides by 140: \[ 100 + x = \frac{6 \times 140}{7} \] \[ 100 + x = 120 \] ### Step 9: Solve for \( x \) \[ x = 120 - 100 = 20 \] ### Final Answer The contractor needs to employ **20 additional men** to complete the work on time. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & DISTANCE

    MOTHERS|Exercise Multiple Choice Question|80 Videos
  • TIME AND WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS |88 Videos

Similar Questions

Explore conceptually related problems

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?

A contractor undertakes to do a piece of work in 40 days.He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time.If he had not engaged the additional men,how many days behind the schedule the work should have been finished? a.5 b.backslash6 c.7 d.8

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extre men should he employ so that the work is completed on time?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

MOTHERS-TIME & WORK-MULTIPLE CHOICE QUESTIONS
  1. 3 men and 4 women together can earn ₹ 3,780 in 7 days, 11 men and 13 w...

    Text Solution

    |

  2. 5 men can do a work in 6 days and 10 women can do the same work in 5 d...

    Text Solution

    |

  3. A contractor undertakes to do a piece of work in 96 days. He engages 1...

    Text Solution

    |

  4. 4 men and 10 women can complete (1)/(3) is part of work in 4 days. No...

    Text Solution

    |

  5. 1 man, 3 women and 4 children can complete a work in 96 hours, whereas...

    Text Solution

    |

  6. 16 women take 12 days to complete a work which can be completed by 12 ...

    Text Solution

    |

  7. 6 Men+10 women can reep 5/12 part of 360 hectare land in 15 days by wo...

    Text Solution

    |

  8. In Nuts And Bolts factory, one machine produces only nuts at the rate ...

    Text Solution

    |

  9. Two pipes A and B can fill a tank in 20 minutes and 30 minutes respect...

    Text Solution

    |

  10. A pipe can fill a tank in 5 hours and a second pipe can empty it in 4 ...

    Text Solution

    |

  11. Two pipes A and B can fill a tank in 60 min. and 75 min. respectively....

    Text Solution

    |

  12. Two taps can fill a tank in 3 hours and 4 hours respectively and a was...

    Text Solution

    |

  13. A tap can fill a cistern in 6 hours. After half of the tank is filled,...

    Text Solution

    |

  14. A pump can fill a cistern in 2 hours. Because of a leak in the cistern...

    Text Solution

    |

  15. A boy and a girl together fill a Hodge. The boy fills 4 liters water i...

    Text Solution

    |

  16. A pipe can fill a cistern in 8 minutes and a waste pipe can empty 6 ki...

    Text Solution

    |

  17. One pipe can fill a tank three times as fast as another pipe. If toget...

    Text Solution

    |

  18. Pipe A can fill a cistern in 4 minutes and pipe B can fill it in 5 min...

    Text Solution

    |

  19. Three pipes A, B and C together can fill a tank in 6 hours. C is close...

    Text Solution

    |

  20. Two pipes A and B can fill a tank in 3 hours and 3 hours 45 minutes re...

    Text Solution

    |