A is 40% more efficient than B and C is ...

A is 40% more efficient than B and C is 20% less efficient than B. Working together, they can complete a task in 20 hours. In how many hours, will A alone can complete 35% of the task?
A, B से 40% अधिक कार्य कुशल है तथा C, B से 20% कम कार्य कुशल है | एक साथ कार्य करते हुए, वे किसी कार्य को 20 घंटों में पूरा कर सकते हैं | A को अकेले इस कार्य का 35% भाग पूरा करने में कितने घंटे लगेंगे ?

A

13

B

15

C

16

D

14

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME & WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS|175 Videos
  • TIMES & DISTANCE

    MOTHERS|Exercise CLASS ROOM EXERCISE |190 Videos

Similar Questions

Explore conceptually related problems

A is 50% more efficient than B and C is 40% less efficient than B. Working together, they can complete a task in 20 days. In how many days will C alone complete 30% of that task? A, B से 50% अधिक कार्य कुशल है तथा C, B से 40% कम कार्य कुशल है | एक साथ कार्य करते हुए, वे किसी कार्य को 20 दिनों में पूरा कर सकते हैं | C अकेले इस कार्य का 30% भाग कितने दिनों में पूरा करेगा ?

A is 50% more efficient than B and C is 40% less efficient than B. Working together, they can complete a task in 10 days. In how many days, will A alone complete 150% of that task? A, B से अधिक कार्य कुशल है और C, B से 40% कम कार्य कुशल है | एक साथ कार्य करते हुए वे किसी कार्य को दस दिनों में पूरा कर सकते हैं | इस कार्य का 150% भाग पूरा करने में A को अकेले कितने दिन लगेंगे ?

A is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a task in 15 days. In how many days, will B alone will complete 75% of the task? A, B से 40% अधिक कार्य कुशल है तथा C, B से 20% कम कार्य कुशल है | एक साथ कार्य करते हुए, वे किसी कार्य को 15 दिनों में समाप्त कर सकते हैं |B अकेले इस कार्य का 75% भाग कितने दिनों में पूरा करेगा ?

A is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a work in 5 days. In how many days, will A alone complete 70% of the work? A, B से 40% अधिक कार्य कुशल है तथा C, B से 20% कम कार्य कुशल है |एक साथ कार्य करते हुए, वे किसी कार्य को 5 दिनों में पूरा कर सकते हैं | A इस कार्य का 70% भाग अकेले कितने दिनों में पूरा करेगा ?

MOTHERS-TIME AND WORK -MULTIPLE CHOICE QUESTIONS
  1. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |

  2. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |

  3. A is 40% more efficient than B and C is 20% less efficient than B. Wor...

    Text Solution

    |

  4. A is 50% more efficient than B and C is 40% less efficient than B. Wor...

    Text Solution

    |

  5. A is 50% more efficient than B and C is 40% less efficient than B. Wor...

    Text Solution

    |

  6. The efficiencies of A, B and C are in the ratio of 2: 3: 5. Working to...

    Text Solution

    |

  7. The efficiencies of A, B and C are in the ratio 2:5:3. Working togethe...

    Text Solution

    |

  8. The efficiencies of A, B and C are in the ratio 2:5:3. Working togethe...

    Text Solution

    |

  9. The efficiencies of A, B and C are in the ratio of 5:3:2. Working toge...

    Text Solution

    |

  10. A earns Rs 180 per hour and works for 7 hours per day. B earns Rs. 160...

    Text Solution

    |

  11. To do a certain work, the ratio of efficiency of A to that of B is 3:7...

    Text Solution

    |

  12. A and B can do a piece of work in 6 days and 8 days, respectively. Wit...

    Text Solution

    |

  13. Pipes A, B and C can fill a tank in 30h, 40 h and 60 h respectively. P...

    Text Solution

    |

  14. A certain number of persons can complete a work in 34 days working 9 h...

    Text Solution

    |

  15. 4 men and 5 women can complete a work in 15 days, whereas 9 men and 6 ...

    Text Solution

    |

  16. Pipes A and B can fill a tank in 16 hours and 24 hours, respectively, ...

    Text Solution

    |

  17. To do a certain work, the ratio of the efficiencies of X and Y is 5:4....

    Text Solution

    |

  18. A can do 40% of a work in 12 days, whereas B can do 60% of the same wo...

    Text Solution

    |

  19. A is as efficient as B and C together. Working together A and B can co...

    Text Solution

    |

  20. A can do one-third of a work in 15 days. B can do 75% of the same work...

    Text Solution

    |