Home
Class 14
MATHS
A can do 40% of a work in 12 days, where...

A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :

A

`2 1/2` days

B

3 days

C

`1 1/2` days

D

2 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will calculate the efficiencies of A, B, and C, the total work done, and then determine how long A, B, and C together will take to complete 28% of the work. ### Step 1: Calculate the efficiencies of A and B 1. **A's Efficiency**: - A can do 40% of the work in 12 days. - Therefore, A can do 100% of the work in \( \frac{12 \text{ days}}{0.4} = 30 \text{ days} \). - A's efficiency = \( \frac{100}{30} = \frac{10}{3} \) % of work per day. 2. **B's Efficiency**: - B can do 60% of the work in 15 days. - Therefore, B can do 100% of the work in \( \frac{15 \text{ days}}{0.6} = 25 \text{ days} \). - B's efficiency = \( \frac{100}{25} = 4 \) % of work per day. ### Step 2: Calculate the combined efficiency of A and B - Combined efficiency of A and B = \( \frac{10}{3} + 4 = \frac{10}{3} + \frac{12}{3} = \frac{22}{3} \) % of work per day. ### Step 3: Calculate the total work done by A and B in 10 days - Work done by A and B in 10 days = \( 10 \times \frac{22}{3} = \frac{220}{3} \) % of work. ### Step 4: Calculate the remaining work - Total work = 100% (or 150 units). - Work completed by A and B = \( \frac{220}{3} \) %. - Remaining work = \( 100 - \frac{220}{3} = \frac{300 - 220}{3} = \frac{80}{3} \) % of work. ### Step 5: Calculate C's efficiency - C completes the remaining work in 4 days. - Therefore, C's efficiency = \( \frac{80/3}{4} = \frac{20}{3} \) % of work per day. ### Step 6: Calculate the combined efficiency of A, B, and C - Combined efficiency of A, B, and C = \( \frac{10}{3} + 4 + \frac{20}{3} = \frac{10 + 12 + 20}{3} = \frac{42}{3} = 14 \) % of work per day. ### Step 7: Calculate the time taken to complete 28% of the work - Work to be completed = 28% of total work = \( 28 \) %. - Time taken = \( \frac{28}{14} = 2 \) days. ### Final Answer A, B, and C together will complete 28% of the work in **2 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS|175 Videos
  • TIMES & DISTANCE

    MOTHERS|Exercise CLASS ROOM EXERCISE |190 Videos

Similar Questions

Explore conceptually related problems

A can do 4/5 of a work in 20 days and B can do 3/4 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 3/4 of the same work in:

A can do 2/5 of a work in 12 days while B can do 66^(2/3)% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

A can do (1)/(3) of a work in 30 days. B can do (2)/(5) of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A can do a work in 4 days while B can do that same work in 6 days. If they worked together, then that work would be completed in

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amita complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:

A can complete one-third of a work in 10 days and B can do ""_(5)^(3) th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do ""_(3)^(2) of the same work?

MOTHERS-TIME AND WORK -MULTIPLE CHOICE QUESTIONS
  1. Pipes A and B can fill a tank in 16 hours and 24 hours, respectively, ...

    Text Solution

    |

  2. To do a certain work, the ratio of the efficiencies of X and Y is 5:4....

    Text Solution

    |

  3. A can do 40% of a work in 12 days, whereas B can do 60% of the same wo...

    Text Solution

    |

  4. A is as efficient as B and C together. Working together A and B can co...

    Text Solution

    |

  5. A can do one-third of a work in 15 days. B can do 75% of the same work...

    Text Solution

    |

  6. Pipes A and B are filling pipes while pipe C is an emptying pipe A and...

    Text Solution

    |

  7. 25 persons can complete a work in 60 days. They started the work. 10 p...

    Text Solution

    |

  8. tank is in the form of a cuboid with length 12m. If 18 kilolitre of wa...

    Text Solution

    |

  9. The efficiencies of A,B and C are in the ratio 4 : 5 : 6. Working toge...

    Text Solution

    |

  10. Two pipes A and B can fill a tank in 6 hours and 9 hours respectively....

    Text Solution

    |

  11. 36 personn working 8 hours a day can do 3 units of working in 12 days....

    Text Solution

    |

  12. Pipes A and B can fill a tank in 6 hours and 9 hours respectively and ...

    Text Solution

    |

  13. Pipes A and B can fill a tank in 6 hours and 8 hours respectively and ...

    Text Solution

    |

  14. 36 persons working 8 hours a day can do 3 units of work in 12 days. Ho...

    Text Solution

    |

  15. The efficiency of A, B and C are in the ratio 5:6:9. Working together,...

    Text Solution

    |

  16. 18 persons working 8 hours a day can complete 3 units of works in 10 d...

    Text Solution

    |

  17. The efficiencies of A, B and C are in the ratio 2 : 5 : 7 working toge...

    Text Solution

    |

  18. Two pipes A and B can fill an empty tank in 10 hours and 16 hours resp...

    Text Solution

    |

  19. Pipes A and B can fill a tank in 12 hours and 16 hours respectively an...

    Text Solution

    |

  20. 16 persons working 6 hours a day can complete a work in 10 days. In ho...

    Text Solution

    |