Home
Class 14
MATHS
A and B. working together, can complete ...

A and B. working together, can complete a work in 16 days, C and A together can complete it in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work ?

A

40

B

36

C

45

D

32

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work efficiencies of A, B, and C based on the information given in the question. ### Step 1: Determine the total work Let’s assume the total work is 96 units (this is chosen as it is the LCM of the days given). ### Step 2: Calculate the work efficiencies 1. **A and B together can complete the work in 16 days:** \[ \text{Efficiency of A + B} = \frac{96}{16} = 6 \text{ units/day} \] 2. **C and A together can complete the work in 32 days:** \[ \text{Efficiency of C + A} = \frac{96}{32} = 3 \text{ units/day} \] 3. **B and C together can complete the work in 24 days:** \[ \text{Efficiency of B + C} = \frac{96}{24} = 4 \text{ units/day} \] ### Step 3: Set up equations From the efficiencies calculated, we can set up the following equations: 1. \( A + B = 6 \) 2. \( C + A = 3 \) 3. \( B + C = 4 \) ### Step 4: Solve the equations We can solve these equations to find the individual efficiencies of A, B, and C. 1. From \( A + B = 6 \) (Equation 1) 2. From \( C + A = 3 \) (Equation 2) - Rearranging gives \( C = 3 - A \) 3. From \( B + C = 4 \) (Equation 3) - Substitute \( C \) from Equation 2 into Equation 3: \[ B + (3 - A) = 4 \implies B = 1 + A \] 4. Substitute \( B = 1 + A \) into Equation 1: \[ A + (1 + A) = 6 \implies 2A + 1 = 6 \implies 2A = 5 \implies A = 2.5 \] 5. Now substitute \( A \) back to find \( B \) and \( C \): \[ B = 1 + 2.5 = 3.5 \] \[ C = 3 - 2.5 = 0.5 \] ### Step 5: Calculate the total efficiency of A, B, and C Now, we have: - Efficiency of A = 2.5 units/day - Efficiency of B = 3.5 units/day - Efficiency of C = 0.5 units/day ### Step 6: Calculate the total work done in 12 days When A, B, and C work together for 12 days: \[ \text{Total efficiency of A + B + C} = A + B + C = 2.5 + 3.5 + 0.5 = 6.5 \text{ units/day} \] \[ \text{Work done in 12 days} = 12 \times 6.5 = 78 \text{ units} \] ### Step 7: Calculate the remaining work \[ \text{Remaining work} = 96 - 78 = 18 \text{ units} \] ### Step 8: Calculate the time taken by C to complete the remaining work Since C's efficiency is 0.5 units/day, the time taken by C to complete the remaining work is: \[ \text{Time} = \frac{\text{Remaining work}}{\text{Efficiency of C}} = \frac{18}{0.5} = 36 \text{ days} \] ### Final Answer C alone will complete the remaining work in **36 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME & WORK

    MOTHERS|Exercise MULTIPLE CHOICE QUESTIONS|175 Videos
  • TIMES & DISTANCE

    MOTHERS|Exercise CLASS ROOM EXERCISE |190 Videos

Similar Questions

Explore conceptually related problems

A and C together can complete a work in 120 days, C and E together can complete the same work in 80 days and A and E together can complete the same work in 160 days. In how many days A, C and E together can complete the same work?

A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?

Anil, Bhuvan and Chirag together can complete a work in 35 days. Anil and Chirag together can complete the same work in 60 days. In how many days Bhuvan alone can complete the same work?

MOTHERS-TIME AND WORK -MULTIPLE CHOICE QUESTIONS
  1. If 30 persons take 10 days to complete a certain work working 8 hours ...

    Text Solution

    |

  2. A , B and C can finish a task in 42 days, 84 days and 28 days, respect...

    Text Solution

    |

  3. A and B. working together, can complete a work in 16 days, C and A tog...

    Text Solution

    |

  4. Pipes A and B can fill a tank in 8 hours and 12 hours, respectively wh...

    Text Solution

    |

  5. A and B together can do a piece of work in 10 days, B and C together c...

    Text Solution

    |

  6. 18 men can complete a work in 9 days. After they have worked for 5 day...

    Text Solution

    |

  7. A can do 40% of a work in 6 days and B can do 30% of the same work in ...

    Text Solution

    |

  8. A, B and c can complete a piece of work in 10, 20 and 60 days respecti...

    Text Solution

    |

  9. A, B and C can complete a piece of worik in 4, 28 and 56 days respecti...

    Text Solution

    |

  10. A, B and C can complete a piece of work in 5, 20 and 60 days respectiv...

    Text Solution

    |

  11. A, B and C can complete a piece of work in 4, 20 and 60 days respectiv...

    Text Solution

    |

  12. A, B and C can complete a piece of work in 4, 20 and 60 days respectiv...

    Text Solution

    |

  13. A and B can complete a piece of work in 15 days and 10 days respective...

    Text Solution

    |

  14. A and B can complete a piece of work in 15 days and 10 days respective...

    Text Solution

    |

  15. A and B can complete a piece of work in 15 days and 10 days respective...

    Text Solution

    |

  16. A and B can complete a piece of work in 15 days and 10 days respective...

    Text Solution

    |

  17. A earns 100 per hour and works for 8 hours per day. Bearns₹ 120per hou...

    Text Solution

    |

  18. If A, B and C can respectively complete a piece of work in 20, 24 and ...

    Text Solution

    |

  19. If 16 men working 12 hours a day can complete a work in 27 days, then ...

    Text Solution

    |

  20. If 40 men working 12 hours a day can complete a work in 8 days, then h...

    Text Solution

    |