12 men complete a work in 18 days. Six d...

12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?

A

10 days

B

12 days

C

15 days

D

9 days

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Standard Level)|37 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Expert Level)|27 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • SET THEORY

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • TIME, SPEED AND DISTANCE

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
DISHA PUBLICATION-TIME AND WORK-Practice Exercise (Foundation Level)
  1. A is 30% more efficient than B. How much time will they, working toget...

    Text Solution

    |

  2. A contractor undertakes to built a walls in 50 days. He employs 50 peo...

    Text Solution

    |

  3. 12 men complete a work in 18 days. Six days after they had started wor...

    Text Solution

    |

  4. A man, a woman or a boy can do a job in 20 days, 30 days or 60 days re...

    Text Solution

    |

  5. 10 men can complete a piece of work in 15 days and 15 women can comple...

    Text Solution

    |

  6. After working for 8 days, Anil finds that only 1/3 of the work has bee...

    Text Solution

    |

  7. A can knit a pair of socks in 3 days. B can knit the same thing in 6 d...

    Text Solution

    |

  8. A can build up a wall in 8 days while B can break it in 3 days. A has ...

    Text Solution

    |

  9. Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient ...

    Text Solution

    |

  10. Three men, four women and six children can complete a work in seven da...

    Text Solution

    |

  11. Sunil and Pradeep can complete a work in 5 days and 15 days respective...

    Text Solution

    |

  12. Suresh can finish a piece of work by himself in 42 days. Mahesh, who i...

    Text Solution

    |

  13. If 6 BSF or 10 CRPF companies can demolish a terrorist outfit in Kashm...

    Text Solution

    |

  14. 2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 b...

    Text Solution

    |

  15. Three pumps working 8 hours a day can empty a tank in 2 day. How many ...

    Text Solution

    |

  16. If 18 binders bind 900 books in 10 days, how many binders will be requ...

    Text Solution

    |

  17. If 27 men take 15 days to mow 225 hectares of grass, how long will 33 ...

    Text Solution

    |

  18. X and Y can do a piece of work in 72 days. Y and Z can do it in 120 da...

    Text Solution

    |

  19. If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 4...

    Text Solution

    |

  20. The work done by man, a woman and a boy are in the ratio 3 : 2 : 1. Th...

    Text Solution

    |