Suresh can finish a piece of work by him...

Suresh can finish a piece of work by himself in 42 days. Mahesh, who is `1/5` times more efficient as Suresh, requires X days to finish the work by working all by himself. Then what is the value of X ?

A

25 days

B

30 days

C

35 days

D

20 days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Standard Level)|37 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Expert Level)|27 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • SET THEORY

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • TIME, SPEED AND DISTANCE

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in x days.If new joins B who is twice as efficient as A,then in How many days can both finish double the work.

X can do a piece of work in 15 days. If he is joined by Y who is 50% more efficient, in what time will X and Y together finish the work?

If a piece of work is finished in 4 days,what part of the work is finished in 1 day

If 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.

30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?

If 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?

DISHA PUBLICATION-TIME AND WORK-Practice Exercise (Foundation Level)
  1. Three men, four women and six children can complete a work in seven da...

    Text Solution

    |

  2. Sunil and Pradeep can complete a work in 5 days and 15 days respective...

    Text Solution

    |

  3. Suresh can finish a piece of work by himself in 42 days. Mahesh, who i...

    Text Solution

    |

  4. If 6 BSF or 10 CRPF companies can demolish a terrorist outfit in Kashm...

    Text Solution

    |

  5. 2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 b...

    Text Solution

    |

  6. Three pumps working 8 hours a day can empty a tank in 2 day. How many ...

    Text Solution

    |

  7. If 18 binders bind 900 books in 10 days, how many binders will be requ...

    Text Solution

    |

  8. If 27 men take 15 days to mow 225 hectares of grass, how long will 33 ...

    Text Solution

    |

  9. X and Y can do a piece of work in 72 days. Y and Z can do it in 120 da...

    Text Solution

    |

  10. If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 4...

    Text Solution

    |

  11. The work done by man, a woman and a boy are in the ratio 3 : 2 : 1. Th...

    Text Solution

    |

  12. Two pipes can fill a cistern in 6 minutes and 7 minutes respectively. ...

    Text Solution

    |

  13. Three pipes A, B and C can fill a tank from empty to full in 30 minute...

    Text Solution

    |

  14. A and B can finish a work in 10 days while B and C can do it in 18 day...

    Text Solution

    |

  15. A certain number of men can do a work in 60 days. If there were 8 men ...

    Text Solution

    |

  16. A and B can do a job in 16 days and 12 days respectively. B has starte...

    Text Solution

    |

  17. Two pipes A and B can fill a tank in 36 minutes and 45 minutes respect...

    Text Solution

    |

  18. A can do a piece of work in 25 days and B in 20 days. They work togeth...

    Text Solution

    |

  19. 12 men complete a work in 18 days. Six days after they had started wor...

    Text Solution

    |

  20. A can do a piece of work in 10 days, while B alone can do it in 15 day...

    Text Solution

    |