Home
Class 14
MATHS
A and B can finish a work in 10 days whi...

A and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ?
A)30 days
B)15 days
C)45 days
D)24 days

A

30 days

B

15 days

C

45 days

D

24 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the efficiencies of A, B, and C based on the information provided. ### Step 1: Determine the total work Let the total work be represented in units. Since A and B can finish the work in 10 days, we can assume the total work is 90 units (as the LCM of 10 and 18 is 90). ### Step 2: Calculate the efficiencies of A, B, and C - **Efficiency of A and B**: They complete the work in 10 days. \[ \text{Efficiency of A and B} = \frac{90 \text{ units}}{10 \text{ days}} = 9 \text{ units/day} \] - **Efficiency of B and C**: They complete the work in 18 days. \[ \text{Efficiency of B and C} = \frac{90 \text{ units}}{18 \text{ days}} = 5 \text{ units/day} \] ### Step 3: Set up equations for individual efficiencies Let the efficiencies of A, B, and C be represented as \(a\), \(b\), and \(c\) respectively: - From the efficiency of A and B: \[ a + b = 9 \quad \text{(1)} \] - From the efficiency of B and C: \[ b + c = 5 \quad \text{(2)} \] ### Step 4: Solve the equations From equation (1), we can express \(a\) in terms of \(b\): \[ a = 9 - b \quad \text{(3)} \] Substituting equation (3) into equation (2): \[ b + c = 5 \implies c = 5 - b \quad \text{(4)} \] ### Step 5: Calculate work done by A, B, and C Now, we analyze the work done: - A worked for 5 days: \[ \text{Work done by A} = 5a \] - B worked for 10 days: \[ \text{Work done by B} = 10b \] - C worked for 15 days: \[ \text{Work done by C} = 15c \] ### Step 6: Total work equation The total work done by A, B, and C must equal 90 units: \[ 5a + 10b + 15c = 90 \] ### Step 7: Substitute values from equations Substituting \(c\) from equation (4) into the total work equation: \[ 5a + 10b + 15(5 - b) = 90 \] Expanding this gives: \[ 5a + 10b + 75 - 15b = 90 \] Simplifying: \[ 5a - 5b + 75 = 90 \] \[ 5a - 5b = 15 \] Dividing by 5: \[ a - b = 3 \quad \text{(5)} \] ### Step 8: Solve for \(a\) and \(b\) Now we have two equations (1) and (5): 1. \(a + b = 9\) 2. \(a - b = 3\) Adding these two equations: \[ 2a = 12 \implies a = 6 \] Substituting \(a\) back into equation (1): \[ 6 + b = 9 \implies b = 3 \] ### Step 9: Find \(c\) Using equation (4): \[ c = 5 - b = 5 - 3 = 2 \] ### Step 10: Calculate the time taken by C alone C's efficiency is \(c = 2\) units/day. To find how many days C would take to finish the whole work: \[ \text{Days taken by C} = \frac{90 \text{ units}}{2 \text{ units/day}} = 45 \text{ days} \] ### Final Answer C alone could finish the whole work in **45 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Standard Level)|37 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Expert Level)|27 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • SET THEORY

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • TIME, SPEED AND DISTANCE

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos

Similar Questions

Explore conceptually related problems

A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in

A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?

DISHA PUBLICATION-TIME AND WORK-Practice Exercise (Foundation Level)
  1. Two pipes can fill a cistern in 6 minutes and 7 minutes respectively. ...

    Text Solution

    |

  2. Three pipes A, B and C can fill a tank from empty to full in 30 minute...

    Text Solution

    |

  3. A and B can finish a work in 10 days while B and C can do it in 18 day...

    Text Solution

    |

  4. A certain number of men can do a work in 60 days. If there were 8 men ...

    Text Solution

    |

  5. A and B can do a job in 16 days and 12 days respectively. B has starte...

    Text Solution

    |

  6. Two pipes A and B can fill a tank in 36 minutes and 45 minutes respect...

    Text Solution

    |

  7. A can do a piece of work in 25 days and B in 20 days. They work togeth...

    Text Solution

    |

  8. 12 men complete a work in 18 days. Six days after they had started wor...

    Text Solution

    |

  9. A can do a piece of work in 10 days, while B alone can do it in 15 day...

    Text Solution

    |

  10. Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in ...

    Text Solution

    |

  11. A can do some work in 24 days, B can do it in 32 days and C can do it ...

    Text Solution

    |

  12. Mayank can do 50% more work than Shishu in the same time. Shishu alone...

    Text Solution

    |

  13. Alord got an order from a garment manufacturer for 480 Denim Shirts. H...

    Text Solution

    |

  14. In a fort there was sufficient food for 200 soldiers for 31 days. Afte...

    Text Solution

    |

  15. Sambhu can do 1/2 of the work in 8 days while kalu can do 1/3 of the w...

    Text Solution

    |

  16. A tank holds 100 gallons of water. Its inlet is 7 inches in diameter a...

    Text Solution

    |

  17. Three diggers dug a ditch of 324 m deep in six days working simultaneo...

    Text Solution

    |

  18. A can do a piece of work in 90 days, B in 40 days and C in 12 days. Th...

    Text Solution

    |

  19. Two forest officials in their respective divisions were involved in th...

    Text Solution

    |

  20. A and B can do a piece of work in 45 and 40 days respectively. They be...

    Text Solution

    |