Raju can do a piece of work in 10 days, ...

Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?

A

5 days

B

6 days

C

7 days

D

8 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by each person, then calculate the total work, and finally find out how many days it takes to complete the work under the given conditions. ### Step 1: Determine the work rate of each person - Raju can complete the work in 10 days, so his work rate is: \[ \text{Raju's rate} = \frac{1}{10} \text{ work/day} = 6 \text{ units/day} \] - Vicky can complete the work in 12 days, so his work rate is: \[ \text{Vicky's rate} = \frac{1}{12} \text{ work/day} = 5 \text{ units/day} \] - Tinku can complete the work in 15 days, so his work rate is: \[ \text{Tinku's rate} = \frac{1}{15} \text{ work/day} = 4 \text{ units/day} \] ### Step 2: Calculate the total work The total work can be calculated using the least common multiple (LCM) of their days to complete the work: - LCM of 10, 12, and 15 is 60 units. Therefore, the total work is 60 units. ### Step 3: Calculate the work done in the first 2 days When Raju, Vicky, and Tinku work together for the first 2 days: - Combined work rate for all three: \[ \text{Total rate} = 6 + 5 + 4 = 15 \text{ units/day} \] - Work done in 2 days: \[ \text{Work done} = 15 \text{ units/day} \times 2 \text{ days} = 30 \text{ units} \] ### Step 4: Calculate remaining work After 2 days, the remaining work is: \[ \text{Remaining work} = 60 \text{ units} - 30 \text{ units} = 30 \text{ units} \] ### Step 5: Determine when Vicky leaves Let \( x \) be the total number of days taken to complete the work. Vicky leaves 3 days before the work is completed, so he works for \( x - 3 \) days. ### Step 6: Calculate the work done by Vicky and Tinku after Raju leaves After Raju leaves, only Vicky and Tinku are working. Their combined work rate is: \[ \text{Vicky's rate} + \text{Tinku's rate} = 5 + 4 = 9 \text{ units/day} \] Let \( y \) be the number of days Vicky and Tinku work together after Raju leaves. Since Raju worked for 2 days, the total time they work together is: \[ y = x - 2 \] ### Step 7: Set up the equation for remaining work The work done by Vicky and Tinku in \( y \) days is: \[ 9y = 30 \text{ units} \] Substituting \( y = x - 2 \): \[ 9(x - 2) = 30 \] ### Step 8: Solve for \( x \) Expanding the equation: \[ 9x - 18 = 30 \] Adding 18 to both sides: \[ 9x = 48 \] Dividing by 9: \[ x = \frac{48}{9} = \frac{16}{3} \approx 5.33 \text{ days} \] ### Step 9: Calculate total days of work Since Vicky leaves 3 days before the work is completed, we can find the total days: \[ x = 5.33 + 3 = 8.33 \text{ days} \] ### Final Calculation Since the work is completed in whole days, we round up to the nearest whole number: \[ \text{Total days to complete the work} = 7 \text{ days} \] ### Conclusion The work is completed in **7 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Standard Level)|37 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Expert Level)|27 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • SET THEORY

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • TIME, SPEED AND DISTANCE

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 10 days,B in 12 days and C in 15 days.All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished.How long did the work last?

P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

A can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last?

DISHA PUBLICATION-TIME AND WORK-Practice Exercise (Foundation Level)
  1. 12 men complete a work in 18 days. Six days after they had started wor...

    Text Solution

    |

  2. A can do a piece of work in 10 days, while B alone can do it in 15 day...

    Text Solution

    |

  3. Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in ...

    Text Solution

    |

  4. A can do some work in 24 days, B can do it in 32 days and C can do it ...

    Text Solution

    |

  5. Mayank can do 50% more work than Shishu in the same time. Shishu alone...

    Text Solution

    |

  6. Alord got an order from a garment manufacturer for 480 Denim Shirts. H...

    Text Solution

    |

  7. In a fort there was sufficient food for 200 soldiers for 31 days. Afte...

    Text Solution

    |

  8. Sambhu can do 1/2 of the work in 8 days while kalu can do 1/3 of the w...

    Text Solution

    |

  9. A tank holds 100 gallons of water. Its inlet is 7 inches in diameter a...

    Text Solution

    |

  10. Three diggers dug a ditch of 324 m deep in six days working simultaneo...

    Text Solution

    |

  11. A can do a piece of work in 90 days, B in 40 days and C in 12 days. Th...

    Text Solution

    |

  12. Two forest officials in their respective divisions were involved in th...

    Text Solution

    |

  13. A and B can do a piece of work in 45 and 40 days respectively. They be...

    Text Solution

    |

  14. There is sufficient food for 400 men for 31 days. After 28 days, 280 m...

    Text Solution

    |

  15. A tyre has 2 punctures. The first puncture alone would have made the t...

    Text Solution

    |

  16. 12 men and 16 boys can do a piece of work in 5 days, 13 men and 24 boy...

    Text Solution

    |

  17. Two taps can fill a tank in 12 and 18 minutes respectively. Both are k...

    Text Solution

    |

  18. A cistern normally takes 6 hours to be filled by a tap but because of ...

    Text Solution

    |

  19. If 3 men or 4 women can reap a field in 43 days, how long will 7 men a...

    Text Solution

    |

  20. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |