If X works 3 times as fast as Y and is a...

If X works 3 times as fast as Y and is able to complete, a work in 40 days less than the number of days taken by Y, then find the time in which they can complete the work working together.

A

15 days

B

10 days

C

`7 (1)/(2)` days

D

5 days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Expert Level)|27 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Foundation Level)|51 Videos
  • SET THEORY

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • TIME, SPEED AND DISTANCE

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos

Similar Questions

Explore conceptually related problems

If X works 3 tims as fast as Y and is able to complete, a work in 40 days less than the number of days taken by Y, then find the time in which they cn complete the work working together.

X works 3 times as fast as Y and is able to complete a work in40 days less than the number of days taken by Y. Find the time in which they can complete the work together.

A is thrice as efficient as B and hence completes a work in 40 days less than the number days taken by B. What will be the number of days taken by both of them when working together ?

A is thrice as efficient as B and hence completes a work in 40 days less than the number of days taken by B. What will be the number of days taken by both of them when working together?

A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?

If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?

DISHA PUBLICATION-TIME AND WORK-Practice Exercise (Standard Level)
  1. There is leak in the bottom of a tank. This leak can empty a full tank...

    Text Solution

    |

  2. A company has a job to prepare certain no. of cans and there are three...

    Text Solution

    |

  3. 3 small pumps and a large pump are filling a tank. Each of the three s...

    Text Solution

    |

  4. A and B can do a job in 15 days and 10 days, respectively. They began ...

    Text Solution

    |

  5. A contract to be completed in 46 days and 117 men were set work, each ...

    Text Solution

    |

  6. If 12 men or 15 women or 18 boys can do a piece of work in 15 days of ...

    Text Solution

    |

  7. The work done by a man, a woman and a child is in the ratio of 3 : 2 :...

    Text Solution

    |

  8. The diameter of three pipes are 1cm, 1 (1)/(3) cm and 2 cm respectivel...

    Text Solution

    |

  9. If X works 3 times as fast as Y and is able to complete, a work in 40 ...

    Text Solution

    |

  10. The Bubna dam has four inlets. Through the first three inlets, the dam...

    Text Solution

    |

  11. Two pipes A and B can fill up a half full tank in 1.2 hours. The tank ...

    Text Solution

    |

  12. Two pipes can fill a cistern in 14 and 16 hours respectively. The pipe...

    Text Solution

    |

  13. Each of A, B and C need a certain unique time to do a certain work. C ...

    Text Solution

    |

  14. All the three taps were open and the emptying pipe is closed. At the t...

    Text Solution

    |

  15. A student studying the weather for d days observed that (i) it rained ...

    Text Solution

    |

  16. The rate of flow of water (in litre per min) of three pipes are 2, N a...

    Text Solution

    |

  17. If 6 BSF or 10 CRPF companies can demolish a terrorist outfit in Kashm...

    Text Solution

    |

  18. Three pumps working 8 hours a day can empty a tank in 2 day. How many ...

    Text Solution

    |

  19. A group of men deaded to do a job in 4 days. But since 20 men dropped ...

    Text Solution

    |

  20. The total number of men, women and children working in a factory is 18...

    Text Solution

    |