Home
Class 14
MATHS
Sixty-four men working 8 h a day plan to...

Sixty-four men working 8 h a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 days. How many hours per day should they need to work in order to achieve the target?

A

11

B

12

C

13

D

15

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Calculate the total work Assume the total work to be 100 units. ### Step 2: Calculate the work done in 5 days The total number of men is 64, and they work 8 hours a day for 5 days. - Work done in 5 days = Number of men × Hours per day × Days worked - Work done = 64 men × 8 hours/day × 5 days = 2560 man-hours ### Step 3: Calculate the percentage of work completed According to the problem, they completed 40% of the work in 5 days. - Work completed = 40% of 100 = 40 units ### Step 4: Calculate the work rate Since they completed 40 units in 2560 man-hours, we can find the work rate. - Work rate = Total work completed / Total man-hours = 40 units / 2560 man-hours = 0.015625 units/man-hour ### Step 5: Calculate the remaining work The remaining work is: - Remaining work = Total work - Work completed = 100 - 40 = 60 units ### Step 6: Calculate the total man-hours needed to complete the remaining work To find out how many man-hours are needed to complete the remaining 60 units: - Total man-hours needed = Remaining work / Work rate = 60 units / 0.015625 units/man-hour = 3840 man-hours ### Step 7: Calculate the daily work hours required to finish the remaining work in 4 days Now, they want to complete the remaining work in 4 days. Let \( H \) be the number of hours they need to work per day. - Total man-hours = Number of men × Hours per day × Days = 64 men × H hours/day × 4 days - Setting this equal to the total man-hours needed: \[ 64 \times H \times 4 = 3840 \] ### Step 8: Solve for \( H \) \[ 256H = 3840 \] \[ H = \frac{3840}{256} = 15 \] ### Conclusion The number of hours per day they need to work to complete the remaining work in 4 days is **15 hours**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • TIME AND WORK

    DISHA PUBLICATION|Exercise Practice Exercise (Standard Level)|37 Videos
  • SET THEORY

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
  • TIME, SPEED AND DISTANCE

    DISHA PUBLICATION|Exercise Test Yourself|15 Videos
DISHA PUBLICATION-TIME AND WORK-Practice Exercise (Expert Level)
  1. A finishes 6/7th of the work in 2z hours, B works twice as fast A and ...

    Text Solution

    |

  2. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  3. The work done by 2 men in a day is equal to the work done by 3 childre...

    Text Solution

    |

  4. It takes 30 hours for an inlet pipe to fill an empty tank completely. ...

    Text Solution

    |

  5. A tank of capacity 25 litres has an inlet and an outlet tap. If both a...

    Text Solution

    |

  6. Ashish, Binay and Joseph can do a job in 20, 30 and 40 days respective...

    Text Solution

    |

  7. Pawan and Qureshi working together can do a piece of work in 10 days w...

    Text Solution

    |

  8. Three cooks have to make 80 idlis. They are known to make 20 pieces ev...

    Text Solution

    |

  9. A cistern has a leak which would empty it in 6 hours. A tap is turned ...

    Text Solution

    |

  10. Tap A can fill a tank in 20 hours, B in 25 hours but tap C can J empty...

    Text Solution

    |

  11. Each of A, B and C need a certain unique time to do a certain work. C ...

    Text Solution

    |

  12. Two men and a woman are entrusted with a task. The second man needs th...

    Text Solution

    |

  13. Two pipes A and B can fill a cistern in 15 hours and ’10 hours respect...

    Text Solution

    |

  14. Working together B and C take 50% more number of days than A,B and C t...

    Text Solution

    |

  15. Eklavya can do the 6 times the actual work in 36 days while Faizal can...

    Text Solution

    |

  16. Sixty-four men working 8 h a day plan to complete a piece of work in 9...

    Text Solution

    |

  17. 4 pipes each of 3 cm diameter are to be replaced by a single pipe disc...

    Text Solution

    |

  18. A can do a job in 3 days less time than B. A works at it alone for 4 d...

    Text Solution

    |

  19. Water flows at 3 metres per sec through a pipe of radius 4 cm. How man...

    Text Solution

    |

  20. A ship 55 km from the shore springs a leak which admits 2 tonnes of wa...

    Text Solution

    |