Home
Class 14
MATHS
If A can complete a project in 3 days, B...

If A can complete a project in 3 days, B can complete the same project in 4 days while C can complete it in 5 days. All of them stated the project together but after 3 days C left, after 4 days B left and after 5 days A left, then how many projects they have finished in 5 days?

A

2

B

1

C

3

D

4

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we first need to determine the work done by each person (A, B, and C) in a day and then calculate how much work they complete together over the specified time. ### Step 1: Determine the work rate of A, B, and C - A can complete the project in 3 days, so A's work rate is: \[ \text{Work rate of A} = \frac{1 \text{ project}}{3 \text{ days}} = \frac{1}{3} \text{ projects per day} \] - B can complete the project in 4 days, so B's work rate is: \[ \text{Work rate of B} = \frac{1 \text{ project}}{4 \text{ days}} = \frac{1}{4} \text{ projects per day} \] - C can complete the project in 5 days, so C's work rate is: \[ \text{Work rate of C} = \frac{1 \text{ project}}{5 \text{ days}} = \frac{1}{5} \text{ projects per day} \] ### Step 2: Find the combined work rate of A, B, and C To find the total work rate when all three work together, we add their individual work rates: \[ \text{Combined work rate} = \frac{1}{3} + \frac{1}{4} + \frac{1}{5} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 3, 4, and 5 is 60. Thus, we convert each fraction: \[ \frac{1}{3} = \frac{20}{60}, \quad \frac{1}{4} = \frac{15}{60}, \quad \frac{1}{5} = \frac{12}{60} \] Now we can add them: \[ \text{Combined work rate} = \frac{20}{60} + \frac{15}{60} + \frac{12}{60} = \frac{47}{60} \text{ projects per day} \] ### Step 3: Calculate the work done in the first 3 days In the first 3 days, all three work together: \[ \text{Work done in 3 days} = 3 \times \frac{47}{60} = \frac{141}{60} \text{ projects} \] ### Step 4: Calculate the work done by B and A after C leaves After 3 days, C leaves. Now A and B continue working together for the next day (Day 4): \[ \text{Work done by A and B in 1 day} = \frac{1}{3} + \frac{1}{4} = \frac{20}{60} + \frac{15}{60} = \frac{35}{60} \text{ projects} \] So, after Day 4, the total work done is: \[ \text{Total work after 4 days} = \frac{141}{60} + \frac{35}{60} = \frac{176}{60} \text{ projects} \] ### Step 5: Calculate the work done by A alone on Day 5 On Day 5, A works alone: \[ \text{Work done by A in 1 day} = \frac{1}{3} = \frac{20}{60} \text{ projects} \] Now, adding this to the total work done: \[ \text{Total work after 5 days} = \frac{176}{60} + \frac{20}{60} = \frac{196}{60} \text{ projects} \] ### Step 6: Calculate the number of complete projects finished To find out how many complete projects they finished, we divide the total work done by the work required for one project: \[ \text{Number of projects completed} = \frac{196}{60} \approx 3.27 \] Since we can only count complete projects, they finished 3 complete projects. ### Final Answer Thus, the total number of projects they have finished in 5 days is **3**. ---
Promotional Banner

Topper's Solved these Questions

  • MENSURATION

    DISHA PUBLICATION|Exercise TEST YOURSELF|15 Videos
  • MOCK TEST - 4

    DISHA PUBLICATION|Exercise Multiple Choice Questions|34 Videos

Similar Questions

Explore conceptually related problems

A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?

A and B complete a piece of work 12 days B and C can complete in 24,days. A and C can complete it in 16 days. In how many days can B alone complete it?

A can complete of a work in 8 days. B can complete 3/5 of the same work in 12 days and C can complete 4/9 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?

A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is

15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when. After 4 days 5 men left the work .

DISHA PUBLICATION-MOCK TEST - 3-Multiple Choice Questions
  1. If highest power of 8 in N! is 19 find highest power of 8 in (N+1)!.

    Text Solution

    |

  2. Find the value of x such that (x+3)(3x-2)^(5)(7-x)^(3)(5x + 8)^(2) ge ...

    Text Solution

    |

  3. If a^(2) + b^(2) = 7ab, then find the value of log(2)((a+b)/(3))

    Text Solution

    |

  4. Find the value of (x^(log y - log z))(y^(log z-log x))(z^(log x - log ...

    Text Solution

    |

  5. Convert (332.22)(4) to base 5.

    Text Solution

    |

  6. Find the value of x such that log(0.3)(x-1) = log(0.09)(x-1).

    Text Solution

    |

  7. If a and b are two negative integers whose difference is 3 and sum of ...

    Text Solution

    |

  8. The total number of ways in which 5 balls of different colours can be ...

    Text Solution

    |

  9. Find the ratio of circum radius (R) to inradius (r) of a triangle whos...

    Text Solution

    |

  10. For a Delta with sides a, b and c, which one of the following statemen...

    Text Solution

    |

  11. If alpha and beta are roots of ax^(2) + bx + c = 0, then find the valu...

    Text Solution

    |

  12. If (p^(2) + 2)x^(2) + 2p^(2)x + (p^(2) - 4) = 0 has roots of opposite ...

    Text Solution

    |

  13. Solve : |x^(2) + 3x| + x^(2) - 2 ge 0

    Text Solution

    |

  14. If A + B = 45^(@), then find the value of (1+tan A)(1+ tan B)

    Text Solution

    |

  15. How many values of [x] exists such that 4{x} = x + [x]

    Text Solution

    |

  16. In how many ways can two squares be chosen on a 8 xx 8 chessboard such...

    Text Solution

    |

  17. Price of two types of rice is 20 and 16 kg. A shopkeeper mixed them in...

    Text Solution

    |

  18. If A can complete a project in 3 days, B can complete the same project...

    Text Solution

    |

  19. If N = 10 ! + 20! + 30! + ……….. + 100 !. Then find the highest power o...

    Text Solution

    |

  20. Solve for x if (x)^(2) + (x+1)^(2) = 25, where (x) denotes the least i...

    Text Solution

    |