How many workers are required for completing the construction work in the 10 days ?
(i) `20%` of the work can be completed by 8 workers in 8 days.
(ii) 20 workers can complete the work in 16 days.
(iii) One - eighth of the work can ve completed by 8 workers in 5 days.

A

(i) only

B

(ii) and (iii) only

C

(iii) only

D

Anyone of the three

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • DATA SUFFICIENCY

    MAHENDRA|Exercise Exercise |40 Videos
  • DATA INTERPRETATION

    MAHENDRA|Exercise EXERCISE |75 Videos
  • INEQUALITY

    MAHENDRA|Exercise Exercise (INEQUALITY)|30 Videos

Similar Questions

Explore conceptually related problems

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

1 man and 1 woman together can complete a piece of work in 8 days. A man alone can complete the work in 10 days. In how many days, can one woman alone complete the work?

In how many days will B alone complete the work? I. A and B together can complete the work in 8 days. II. B and C together can complete the work in 10 days. III. A and C together can complete the work in 12 days

12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

If A can complete work in 6 days, B can complete the work in 8 days and C can complete the same work in 12 days. In how much time A, B, and C can complete the work.

In how many days can 4 women complete a work? I. 4 men and 4 women can complete the same work in 12 days. II. 10 women can complete the same work in 16 days

A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

MAHENDRA-DATA SUFFICIENCY -Exercise
  1. Twons A,B and C are on a straight line. Town C is between A and B. The...

    Text Solution

    |

  2. What is the average speed of the car over the entire distance ? (i...

    Text Solution

    |

  3. What was the speed of the running train ? (i) Length of the train wa...

    Text Solution

    |

  4. What is the speed of running train which train which takes 9 seconds t...

    Text Solution

    |

  5. What is the length of a running train ? (i) The train crosses a man ...

    Text Solution

    |

  6. What is the rate of simple interest ? (i) The total interest earned ...

    Text Solution

    |

  7. The simple interest on a sum of money is Rs. 50 What is the sum ? (i...

    Text Solution

    |

  8. How much money did X invest ? (i) An increase in the rate in interes...

    Text Solution

    |

  9. What percentage of simple interest per annum did Anand pay to Deepak ?...

    Text Solution

    |

  10. What is the rate of compound interest ? (i) The principal was invest...

    Text Solution

    |

  11. What is the area of the rectangle ? (i) the difference between the ...

    Text Solution

    |

  12. What is R's share on profit a joint venture ? (i) Q started business...

    Text Solution

    |

  13. What is the difference in the share of profit between P and Q in joint...

    Text Solution

    |

  14. A,B and C together start a business with a total investment of Rs. 15,...

    Text Solution

    |

  15. How many workers are required for completing the construction work in ...

    Text Solution

    |

  16. In how manu days can the work be done by 9 men and 15 women ? (i) 6 ...

    Text Solution

    |

  17. In how many days 10 women can finish the work I. 10 men finish the w...

    Text Solution

    |

  18. What is the speed of the train ? (i) the train crosses 300 metres lo...

    Text Solution

    |

  19. What is the speed of the train ? (i) the train crosses a signal pole...

    Text Solution

    |

  20. What is the length of the train X ? (i) Train X crosses a telegraph ...

    Text Solution

    |