A and B together can finish a job in 24 ...

A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. Calone will finish the job in

A

12 days

B

14 days

C

16 days

D

24 days

Text Solution

Verified by Experts

Promotional Banner

Similar Questions

Explore conceptually related problems

A and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in

A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?

A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.

A and B together can do a piece of work in 20 days, while B and C together can do the same work in 15 days. If A ,B and C together can finish this work in 10 days, then find the number of days in which B alone can finish the work.

A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require?

(A + B) together can complete a job in 8 days. Both B and C working alone can finish the same job in 12 days. A and B commence work on the job and work for 4 days, where upon A leaves, B continues for 2 more days and then he leaves too, C now starts working and finishes the job, how many days will C require ?