A can do a piece of work in 20 days and ...

A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in

A

(A) 5 days

B

(B) 6 days

C

(C) 10 days

D

(D) 12 days

Text Solution

AI Generated Solution

Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a piece of work in 12 days and B in 15 days. With help of C, they finish the work in 4 days. In how many days C alone can do the same work?

A can do a piece of work in 10 days and B in 12 days. With help of C, they finish the work in 4 days. In how many days C along can do the same work?

A can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?

A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish it in 5 days. If they are paid Rs 960 for the whole work how much money A gets ?

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :