A alone can complete a work in 12 days. ...

A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?

A

24 days

B

18 days

C

16 days

D

20 days

Text Solution

Verified by Experts

Promotional Banner

Similar Questions

Explore conceptually related problems

A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?

A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?

A and B working together can do a piece of work in 12 days and A alone can caomplete the work in 18 days. How long will B alone take to complete the job?

Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?

A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?