If 10 men can do a piece of work in 12 d...

If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be

A

12 days

B

10 days

C

9 days

D

8 days

Text Solution

Verified by Experts

Promotional Banner

Similar Questions

Explore conceptually related problems

If 8 men can do a piece of work in 14 days, then in how much time (in days) will 7 men do the same piece of work?

If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :

If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

If 52 men can do a piece of work in 35 days in how many days 28 men will do it?

4 men & 18 women can do a piece of work in 2.5 days, then in how many days 12 woment can complete the same piece of work ? A. Ratio of efficiency of men to woment is 3:2. B. 6 men & 6 women can complete the dame work in 4 days.