A and B can do a job together in 12days . A is 2 times as efficient as B . In how many days can B alones complete the work ?

A

36

B

12

C

18

D

9

Text Solution

Verified by Experts

Promotional Banner

Similar Questions

Explore conceptually related problems

A alone can do a work in 15 days. A is 20% less efficient than B. In how many days can B alone do the work?

A and B can do a work in 8 days and A alone can do it in 12 days. In how many days can B alone do it?

A and B together can do a job in 12 days. B alone can finish it in 28 days. In how many days can A alone finish the work? (a)21 days (b)19 days (c)20 days (d)none of these

A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?