Arun and Amit can do a piece of work in ...

Arun and Amit can do a piece of work in 9 days and 12 days respectively. If they work alternate days and Amit starts the work first, then inhow many days `frac(35)(36)` parts of whole work will be completed?

A

10 days

B

12 days

C

5 days

D

8 days

Text Solution

AI Generated Solution

Promotional Banner

Similar Questions

Explore conceptually related problems

Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?

A and B can complete a piece of work in 4 days and 8 days, respctively. They work on alternate days and A starts the work. In how work in may days will the work be completed

A and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?