A man completes a work in 10 days by doing 5 hours per day. By doing 7 hours per day, he can complete this work in -

A

12 days

B

10 days

C

7 days

D

None of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will use the formula that relates the amount of work done in terms of man-days and hours worked. ### Step 1: Understand the given information - A man completes a work in 10 days by doing 5 hours per day. - We need to find out how many days he will take to complete the same work if he works 7 hours per day. ### Step 2: Define the variables - Let \( M_1 \) = 1 (the man) - \( D_1 \) = 10 days (the time taken in the first scenario) - \( H_1 \) = 5 hours (the hours worked per day in the first scenario) In the second scenario: - \( M_2 \) = 1 (the same man) - \( D_2 \) = ? (the time taken in the second scenario, which we need to find) - \( H_2 \) = 7 hours (the hours worked per day in the second scenario) ### Step 3: Use the formula The formula relating the work done is: \[ M_1 \times D_1 \times H_1 = M_2 \times D_2 \times H_2 \] ### Step 4: Substitute the known values Substituting the known values into the formula: \[ 1 \times 10 \times 5 = 1 \times D_2 \times 7 \] This simplifies to: \[ 50 = D_2 \times 7 \] ### Step 5: Solve for \( D_2 \) To find \( D_2 \), divide both sides by 7: \[ D_2 = \frac{50}{7} \] ### Step 6: Calculate \( D_2 \) Calculating \( D_2 \): \[ D_2 \approx 7.14 \text{ days} \] Thus, the man can complete the work in approximately \( \frac{50}{7} \) days or about 7.14 days. ### Final Answer The man can complete the work in \( \frac{50}{7} \) days. ---
Promotional Banner

Topper's Solved these Questions

  • PRACTICE SET-2

    UPKAR PUBLICATION |Exercise PART-III Quantitative Aptitude|50 Videos
  • PRACTICE SET 10

    UPKAR PUBLICATION |Exercise PART - III QUANTATIVE APTITUDE |50 Videos
  • PRACTICE SET-3

    UPKAR PUBLICATION |Exercise PART-III QUANTIATIVE APTITUTE|50 Videos

Similar Questions

Explore conceptually related problems

By working 8 hours a day. A can complete a work in 10 day. If the reduces the work hours by 3 hours per day, them he can complete the same work in ……………….. Days.

By working 8 hours a day. A can complete a work in 10 day. If the reduces the work hours by 3 hours per day, them he can complete the same work in ……………….. Days.

Mohan can complete his work in 3 days by doing 2 hours per day. How much work can be complete in one day ?

Working 2 hours in a day, P can complete a work in 10 days and working 5 hours in a day, Q can complete the same work in 6 days. Working 3 hours in a day, in how many days both P and Q together can complete the same work?

UPKAR PUBLICATION -PRACTICE SET-2-PART-III Quantitative Aptitude
  1. A man has 3 bags costed Rs.30 each. In how much amount should be sell ...

    Text Solution

    |

  2. The ratio of two numbers is 2:3. If 20 is subtracted by each number, t...

    Text Solution

    |

  3. A man completes a work in 10 days by doing 5 hours per day. By doing 7...

    Text Solution

    |

  4. If the cost price of 3 items is equal to selling price of 5 items. How...

    Text Solution

    |

  5. A square of 100 metre perimeter has it's area -

    Text Solution

    |

  6. What will be the average of first 20 odd numbers ?

    Text Solution

    |

  7. In how many years, the interset of a money will be 3 times of the mone...

    Text Solution

    |

  8. If 16% of x = 48% of y, then x:y will be -

    Text Solution

    |

  9. A circle of 2pi metre perimeter has it's area -

    Text Solution

    |

  10. If x^(1/2)= sqrt(11) then, value of x will be -

    Text Solution

    |

  11. Printed rate of a book is Rs. 250 and available at Rs. 225 . What is t...

    Text Solution

    |

  12. If P^(-1//2) = (1/(25))^(2) , then the value of P will be -

    Text Solution

    |

  13. The cost of 3 1/2 metre sheet is Rs.150, what will be the cost of 1 me...

    Text Solution

    |

  14. A boat can bear the weight of 4 men or 12 boys . How many boys can go ...

    Text Solution

    |

  15. If P- 1/P = 6 , then the value of P^2 + 1/P^2 will be -

    Text Solution

    |

  16. Number of primes between 1 to 100 is .

    Text Solution

    |

  17. I is -

    Text Solution

    |

  18. A irrational number can be rational by the process of -

    Text Solution

    |

  19. If n is a whole number greater than 1, then n^2 (n^2- 1) is always div...

    Text Solution

    |

  20. sqrt(6+sqrt(6+sqrt(6+……))) is equal to

    Text Solution

    |