Home
Class 14
MATHS
A contractor undertook to finish a work ...

A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done `(3)/(5)` part of the work, the number of men he can withdraw so that the work may still be finished in time is :

A

30

B

45

C

40

D

35

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • PRACTICE SET-8

    UPKAR PUBLICATION |Exercise PART-III QUANTITATIVE APTITUDE |39 Videos
  • PROBABILITY

    UPKAR PUBLICATION |Exercise QUESTION BANK|110 Videos

Similar Questions

Explore conceptually related problems

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 2/3 of the work. How many men can be discharged now so that the work inay finish in time?

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extre men should he employ so that the work is completed on time?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is: (A) 50 (B) 75 (C) 100 (D) 150

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that (1)/(3)rd of the work was still to be done. How many more men were required to complete the work in stipulated time?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?

UPKAR PUBLICATION -PRACTICE SET-9-Part- III (Quantative Aptitude )
  1. If 5.5 of a= 0.65 of b, then a : b is equal to—

    Text Solution

    |

  2. An article is sold at a loss of 10%. Had it been sold for 90 more, the...

    Text Solution

    |

  3. A contractor undertook to finish a work in 92 days and employed 110 me...

    Text Solution

    |

  4. From a class of 42 boys, a boy aged 10 years goes away and in his plac...

    Text Solution

    |

  5. What is to be added to 15% of 160 so that the sum may be equal to 25% ...

    Text Solution

    |

  6. Two trains start from station A and B and travel towards each other at...

    Text Solution

    |

  7. The bar diagram below shows the production of patatoes (in quintal) fr...

    Text Solution

    |

  8. The bar diagram below shows the production of potatoes (in quintals) f...

    Text Solution

    |

  9. If the ratio of two numbers is 2 : 1 and their product is 1800, then t...

    Text Solution

    |

  10. In a lake, there are 10 steps labelled using alphabets from A to J. St...

    Text Solution

    |

  11. In a family there are several brothers and sisters. Every 2 boys have ...

    Text Solution

    |

  12. Rohan ranks seventh from the top and twenty-sixth from the bottom in a...

    Text Solution

    |

  13. If ‘a’ means ‘/, 'b' means 'x’.‘c' means '+'. ‘d’ means ‘-’, then find...

    Text Solution

    |

  14. When I started from home, the ail tank of car was 4/5 full. After con...

    Text Solution

    |

  15. In each of the following Questions a word has been given. followed by ...

    Text Solution

    |

  16. When a number is divided by another number, the remainder is 23. When ...

    Text Solution

    |

  17. On dividing a number by 13, we get 1 as remainder. If the quotient is ...

    Text Solution

    |

  18. Find three rational numbers between 2.5 and 3-

    Text Solution

    |

  19. The value of root 4((81)^(-2)) is

    Text Solution

    |

  20. 2sqrt3-sqrt3-3sqrt3+sqrt(12) is equal to

    Text Solution

    |