Home
Class 14
MATHS
76 ladies complete a job in 33 days.Due ...

76 ladies complete a job in 33 days.Due to some reason some ladies did not join the work and therefore it was completed in 44 days. The number of ladies who did not report for the work is

A

17

B

18

C

19

D

20

Text Solution

AI Generated Solution

Promotional Banner

Similar Questions

Explore conceptually related problems

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:

35 boys can do a piece of work in 15 days. The work will completed in 25 days. How many boys did not turn up for the job?

A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is

Two workers 'A' and 'B' working together completed a job in 5 days. Had 'A' worked twice as efficiently as he actually did, the work would have completed in 3 days. In how many days could 'A' alone complete the job ?

A worker has to complete a job of 175 units. On each day starting from the second, he does 75% of the part of the job he did on the previous day. Find the number of days in which the job is completed if he did 36 units of work on the 3rd day.

X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in