A' can do a piece of work in x days and ...

A' can do a piece of work in x days and B can do the same work 3x days. To finish the work together they take 12 days. What is the value of x>.

A

8

B

10

C

12

D

16

Text Solution

Verified by Experts

Promotional Banner

Similar Questions

Explore conceptually related problems

If A can do a piece of work in p days and B can do the same in q days: A and B together can finish it in how many days

A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?

A can do a piece of work in 9 days and B can do the same work in 15 days. If they work together, in what ratio A and B will receive their wages?

Deepak can do a piece of work in 25 days and Ashok can do the same work in 40 days.They work together for 5days and then Deepak goes away.In how many days will Ashok finish the remaining work?

P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :